Thursday, October 15, 2026TheUtah Ledger

Everything Utah, every day.

Orem development tracker

Wastewater treatment plant upgrades

A 20-year, four-phase master plan to replace aging equipment and meet environmental limits at the water reclamation plant serving Orem, Lindon and part of Vineyard. Phase 1 is projected at $95.4 million including engineering, to be financed with Orem utility bonds, with costs shared by capacity rights.

Where it stands
In review
Type
Public project
Location
Orem water reclamation plant

Every hearing and vote

  1. June 15, 2026 · City Council work session

    Wastewater treatment plant upgrades and cost sharing

    Discussed

    Orem Public Utilities Director Reed Price said Orem's plant treats all of Lindon's wastewater, about 9 million gallons a day, 13 percent of it from Lindon. A 20-year, four-phase master plan valued at $160 million in 2022 now has a first phase of $88.8 million in construction plus $6.6 million in engineering, $95.4 million in all, up from an earlier $58 million estimate. Price estimated 25 to 30 percent of the cost is driven by environmental mandates. Shares follow capacity rights: Orem 85.68 percent (about $81.8 million), Lindon 12.24 percent ($11.7 million) and Vineyard 2.08 percent (nearly $2 million). Orem plans revenue bonds backed by its AAA utility rating; Lindon is weighing joining the bond or repaying Orem over time at a rate tied to the Public Treasurers' Investment Fund. No vote was taken.