American Fork · Planning Commission work session

UTA outlines FrontRunner double-tracking through American Fork; code items pulled from joint session

January 20, 2026, 4:00 p.m. · City Administration Conference Room, 51 E. Main St.

A scheduled joint work session of the American Fork City Council and Planning Commission on the polycentric plan and code amendments became a single presentation on FrontRunner 2X after both planning items were pulled. UTA and UDOT officials said the roughly $3.2 billion project would double-track most of Utah County, including two segments in American Fork, with strip property purchases of about 15 to 20 feet, construction starting in 2027 and 15-minute peak service by 2030. The minutes list no planning commissioners present.

From the approved minutes.

In brief

2 items came up for a decision or discussion: 1 no action and 1 discussed.

The agenda records 1 dollar amount, the largest $3.2 billion.

2 items here are tracked in the city's development tracker.

This write-up links 2 source documents.

3 members were present and 3 absent (Councilmember Ryan Hunter, Councilmember Ernie John, Councilmember Clark Taylor).

The previous Planning Commission work session meeting was on January 7, 2026: Planning commission meeting canceled

The next one was on January 21, 2026: Planning commission recommends Scott zone change for three-lot subdivision at 672 W. 750 North

Decisions at a glance

Agenda, item by item

  1. Item 1-2 · Other

    Polycentric plan and municipal code amendments

    No action

    Both items were removed from the agenda.

  2. Item 3 · Roads and utilities

    FrontRunner 2X project presentation

    Discussed · FrontRunner corridor through American Fork (Storrs Avenue to Pioneer Crossing; American Fork Station on 200 South)

    UTA project manager Janelle Robertson, deputy Matt Carter, consultant Terry Warner and outreach lead Muriel Xochimitl said UDOT manages the project with UTA. It adds 11 double-track segments, a Bluffdale station and 10 diesel multiple-unit trains (likely Stadler) to double service to every 15 minutes at peak. American Fork has two segments, including about 4.4 miles north of the station to Pioneer Crossing; acquisitions would be 15- to 20-foot strips with no full takings, plus work on American Fork River bridges and crossings such as Storrs Avenue, retaining walls by the Timpanogos Special Service District, and coordination with the planned 1100 South roundabout near Auto Mall Drive. Two homes near Storrs may get noise mitigation such as new windows. Mayor Frost urged moving the poorly located American Fork station and buying land for parking; City Administrator David Bunker said 200 South will be widened with a center cycle track and two lanes each side.

    • Total cost: about $3.2 billion (incl. 40% FTA contingency)
    • State funding: about $840 million; rest from pending FTA core capacity grant
    • Design-builder: Frontrunner Forward Partners (Stacy Witbeck Inc. and Ralph L. Wadsworth Construction JV) with Horrocks/DEA design
    • Construction start expected 2027; revenue service 2030
    • No federal money for station relocation

    Follow FrontRunner double tracking (FR2X) utility relocations in the development tracker →

    Follow 200 South widening (Patriot Station CRA) in the development tracker →