Park City development tracker

Upper Main Street improvement project

Widened sidewalks, trail connections and separated intersections on Upper Main and Hillside, split in two phases. Phase one is estimated at $1 million; in December 2022 council members agreed to proceed with phase one.

Approved

Type
Road project
Applicant
Park City Municipal
Location
Upper Main Street, Swede Alley, Park Avenue, Daly Avenue, King Road
  1. May 25, 2023City Council: Stanley Consultants addendum for Upper Main Street improvements
  2. Apr 27, 2023City Council: Upper Main Street improvements construction agreement
  3. Dec 8, 2022City Council: Upper Main Street improvement project

In brief

Upper Main Street improvement project appears on 3 recorded agendas, from the City Council meeting of December 8, 2022 to the City Council meeting of May 25, 2023.

On record, it was approved 2 times.

The most recent decision was approved (3-0-1) at the City Council meeting of May 25, 2023.

Follow the money and project delivery

Upper Main Street improvement project

Approved

  1. Council action

    Approved: Stanley Consultants addendum for Upper Main Street improvements · Approved minutes Record → · May 25, 2023

  2. Money in the record

    change-order: $489,200 — Addendum for Upper Main Street improvements (not to exceed) Record → · May 25, 2023

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. May 25, 2023 · City Council

    Stanley Consultants addendum for Upper Main Street improvements

    Approved · 3-0-1

    Adds scope to the design agreement. Phase two, the Main and Swede Alley intersection, is delayed for lack of community consensus; the city manager said the project was reduced by 20 percent. Rubell wanted total project costs shown rather than piecemeal figures and abstained, with no reason recorded. Staff will give a six-month capital transportation update on June 22.

    Moved by Council Member Max Doilney, seconded by Council Member Tana Toly. Vote: 3-0; Rubell abstained

  2. April 27, 2023 · City Council

    Upper Main Street improvements construction agreement

    Approved · 5-0

    Construction is expected to start in June, with Main Street reduced to one lane with alternating traffic and the trolley continuing. Two residents opposed, one saying only three of nine adjacent owners had spoken with staff. Lighting is not included but conduits will be installed.

    Moved by Council Member Ryan Dickey, seconded by Council Member Becca Gerber. Vote: 5-0

  3. December 8, 2022 · City Council

    Upper Main Street improvement project

    Discussed

    After six focus group meetings, the proposal includes widened sidewalks on Upper Main and Hillside, trail connections and separated intersections near Main Street, Swede Alley, Park Avenue, Daly Avenue and King Road. Phase one is estimated at $1 million; phase two covers the Swede Alley and Main Street intersection. Council members agreed to proceed with phase one and the preferred design; no formal vote.