Lower Park Avenue improvement project
A street reconstruction project with outreach beginning August 2022, design and utility relocation in 2023 and construction planned for 2024. Council approved a $60,000 public involvement contract.
Approved
- Type
- Road project
- Location
- Lower Park Avenue
- Applicant
- Park City Municipal
- City Council: Transportation capital project funding direction
- City Council: Transportation capital program overview
- City Council: Lower Park Avenue improvement project public engagement
- City Council: Avenue Consultants public involvement for Lower Park Avenue project
In brief
Lower Park Avenue improvement project appears on 4 recorded agendas, from the City Council meeting of July 14, 2022 to the City Council meeting of April 25, 2024.
On record, it was approved once.
The most recent decision was approved (4-0) at the City Council meeting of July 14, 2022.
Follow the money and project delivery
Lower Park Avenue improvement project
- Council action
Approved: Avenue Consultants public involvement for Lower Park Avenue project · Approved minutes Record → · July 14, 2022
- Money in the record
contract: $60,000 — Lower Park Avenue public involvement (not to exceed) Record → · July 14, 2022
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
April 25, 2024 · City Council
Transportation capital project funding direction
Discussed
Snow Creek crossing: staff did not recommend an at-grade crossing now; Ciraco and Parigian supported a traffic study and pausing spending on the tunnel, which speakers said has grown from about $5 million to over $18 million; council agreed to improve the Yarrow side before pursuing tunnel funding. Lower Park Avenue: Dias will return with options at $8 million to $10 million. Budget placeholders of $12 million for Lower Park Avenue and $18.5 million for Snow Creek were agreed, with no spending authorized. Direction only; no motion.
January 16, 2024 · City Council
Transportation capital program overview
Discussed
Projects reviewed included bus stop improvements, Thaynes and Three Kings pathways, Lower Park Avenue, the Snow Creek crossing tunnel and Homestake Road reconstruction. The city receives $3 million to $10 million a year in transportation grants; a $1.4 million Quinn's park-and-ride grant was redirected to a higher priority and the regional council granted $1 million for SR-224 and SR-248 right-of-way. Council favored continuing to pursue grants while staying open to other funding. No vote.
February 2, 2023 · City Council
Lower Park Avenue improvement project public engagement
Discussed
The project covers Park Avenue from Empire to Heber with utility upgrades and road reconstruction. A survey drew 378 responses; residents valued access, pedestrian and cyclist safety and neighborhood character and liked pilot planter boxes. Design is in 2023 with construction beginning next year. No action.
July 14, 2022 · City Council
Avenue Consultants public involvement for Lower Park Avenue project
Approved · 4-0
Outreach starts in August; design and utility relocation are planned for 2023 and construction in 2024. Staff said the project is major and warrants outside help. Rubell asked that collected data identify its source.