3900 South reconstruction

Joint 3900 South reconstruction with Millcreek; update on the October 7, 2021 agenda.

Where it stands
Under construction
Type
Road project
Location
3900 South

Every hearing and vote

  1. January 23, 2020 · City Council

    Work meeting: 3900 South reconstruction, Holladay@20 and council policies

    Discussed

    Engineers presented the 3900 South reconstruction from 2300 East to Wasatch Boulevard. The Holladay@20 Citizen Advisory Group said the city has $63 million in unfunded capital projects. Council Member Petersen wanted more information before deciding on the Village height request, and staff will return with language on allowing council members enrolled in the state retirement system to make salary contributions. No action was taken.

  2. May 7, 2020 · City Council

    City manager report

    Discussed

    Staff are acquiring temporary construction easements for the 3900 South project, the Highland Drive project is expected to go to bid within four weeks, and the Gunderson safe sidewalks project received additional UDOT funding so a contract can be awarded.

  3. May 28, 2020 · City Council

    City manager report

    Discussed

    Salt Lake County will share CARES Act funds, with Holladay expecting about $900,000 for qualifying expenses such as remote-meeting technology and cleaning. Fourth of July festivities were canceled. Right-of-way work on the 3900 South project is being finalized with advertising for bids next. The police chief said operations are back to normal and speeding complaints have increased.

  4. June 4, 2020 · City Council

    City manager report

    Discussed

    Completion of the 3900 South project is now expected around December 2020 because of utility work and Dominion Energy line replacement, with bidding imminent. Plaza bollards are delayed 14 weeks and bike racks have no set timeline.

  5. January 7, 2021 · City Council

    Work meeting: ethics training, council policies, fraud assessment, 3900 South

    Discussed

    The city attorney reviewed open meetings and ethics rules, recommending recusal where a member is involved. The council reviewed policy sections including raising a spending threshold from $500 to $1,000. Holladay scored 330 of 395 on a state fraud-risk checklist, a low-risk category. The city manager said the joint 3900 South reconstruction with Millcreek begins in February.

  6. February 4, 2021 · City Council

    City manager report

    Discussed

    Work on the 3900 South reconstruction begins February 15 and should finish by year-end. A proposed transportation funding bill would provide about $250,000 a year for 15 years. Staff was watching bills on building inspections, billboards and accessory dwelling units.

  7. February 18, 2021 · City Council

    City manager report

    Discussed

    The 3900 South project begins on the east end with a proposed 25 mph construction zone, and the Highland Drive intersection project starts March 15 for completion in mid-July. A pickleball court acrylic overlay was estimated at $15,000 with a 7 to 10 year lifespan. Police arrested a fraud suspect in a case with over 100 victims.

  8. April 1, 2021 · City Council

    Resolution 2021-07: Micro-surface agreement with Millcreek (3900 South, east of Highland Drive to 2300 East)

    Approved · 6-0

    The city manager said this is the city's first use of micro-surface pavement treatment, which extends pavement life. No dollar amount is stated in the minutes.

    Moved by Council Member Paul Fotheringham, seconded by Council Member Sabrina Petersen. Vote: 6-0; the minutes record the mayor voting with the council

  9. October 7, 2021 · City Council

    City manager report: 3900 South and skate park

    Pending

    Updates on the 3900 South project and the skate park.