Holladay development tracker

Highland Drive corridor study

Corridor study with two alternatives (complete street, or five lanes with a multi-use pathway). Construction was estimated at $21.5 million; a regional grant application is planned for fall 2022.

Approved

Type
Road project
Location
Highland Drive
  1. May 16, 2024City Council: Ratify interlocal agreement with Salt Lake County for Highland Drive corridor preservation at…
  2. Mar 21, 2024City Council: Work meeting: 3900 South trail, Highland Drive and sidewalks
  3. Mar 7, 2024City Council: Work meeting: police restructuring, paving and curb and gutter
  4. Jul 13, 2023City Council work session: Work meeting: Highland Drive funding, housing report, City Hall and flood property
  5. Apr 20, 2023City Council: City manager report: flood update and Highland Drive

In brief

Highland Drive corridor study appears on 6 recorded agendas, from the City Council meeting of June 16, 2022 to the City Council meeting of May 16, 2024.

On record, it was approved once.

The most recent decision was approved (6-0) at the City Council meeting of May 16, 2024.

Follow the money and project delivery

Highland Drive corridor study

Approved

  1. Council action

    Approved: Ratify interlocal agreement with Salt Lake County for Highland Drive corridor preservation at 4504 South Highland Drive · Approved minutes Record → · May 16, 2024

  2. Money in the record

    land: $64,000 — Property acquisition for Highland Drive corridor preservation Record → · May 16, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. May 16, 2024 · City Council

    Ratify interlocal agreement with Salt Lake County for Highland Drive corridor preservation at 4504 South Highland Drive

    Approved · 6-0

    A $64,000 property acquisition for corridor preservation.

    Moved by Council Member Ty Brewer, seconded by Council Member Drew Quinn. Vote: 6-0; unanimous

  2. March 21, 2024 · City Council

    Work meeting: 3900 South trail, Highland Drive and sidewalks

    Discussed

    The state transportation department has committed $10 million to the 3900 South trail, with preliminary estimates. Staff recommended the five-lane Highland Drive option at about $30 million. Sidewalk funding is $100,000 to $300,000 a year, so build-out could take about 10 years. Council Member Quinn reported a $2 million EPA grant application for Utah Renewable Communities.

  3. March 7, 2024 · City Council

    Work meeting: police restructuring, paving and curb and gutter

    Discussed

    A police board special meeting was set for March 13 ahead of an interlocal agreement vote, with a 9.7% health insurance increase pending review. The curb and gutter bond budget is $850,000, with $340,000 spent and $510,000 remaining; an assessment found $896,000 in repairs, narrowed to $504,000. The city manager reported a Safe Routes to School award of just over $700,000 for 2700 East Phase 2, a $3.6 million federal earmark and a $1.23 million state appropriation for Highland Drive.

  4. July 13, 2023 · City Council work session

    Work meeting: Highland Drive funding, housing report, City Hall and flood property

    Discussed

    The House Transportation Subcommittee recommended $3.6 million for Highland Drive pre-design and right-of-way work, with the project estimated at about $30 million. Staff sought approval to demolish structures on city-owned flood-mitigation property at 1770 Holladay Boulevard, and the council supported it with a request for proposals to follow. A City Hall seismic evaluation was estimated at about $1.1 million, with staff expecting under $2 million. About 25% of Holladay households pay more than 30% of income toward housing.

  5. April 20, 2023 · City Council

    City manager report: flood update and Highland Drive

    No action

    Nearly 400 volunteers filled 4,000 to 5,000 sandbags, with another sandbag event April 29 at Knudsen Park. A $3.6 million funding request for Highland Drive reconstruction was submitted to the House Appropriations Committee. No vote was taken.

  6. June 16, 2022 · City Council

    Work meeting: Highland Drive study and skate park concept

    Discussed

    Staff estimated construction at $21.5 million including a 30% contingency; burying utilities would cost about $8 million versus $280,000 to relocate them, and the council's sense was that burial was not feasible without other funding. A survey found 42% for a complete street alternative and 52% for a five-lane alternative with a multi-use pathway. A grant application to the Wasatch Front Regional Council is planned for fall 2022. No votes were taken.