Logan development tracker

Second Dam sediment removal

On Jan. 16, 2024 the Logan Municipal Council approved Resolution 24-02, a budget adjustment that included $1,400,000 of additional funding for the Second Dam sediment removal project, to remove additional sediment left by last year's spring runoff.

ApprovedStatus as of Jan 16, 2024

Type
Public project
Location
Second Dam, Logan River
Applicant
City of Logan Light & Power
  1. Jan 16, 2024City Council: Budget adjustments, Resolution 24-02 (public hearing)
  2. Jan 2, 2024City Council: Workshop: budget adjustments, Resolution 24-02
  3. Oct 17, 2023City Council: Budget adjustments, Resolution 23-43 (public hearing)
  4. Oct 3, 2023City Council: Workshop: budget adjustments, Resolution 23-43
  5. Feb 7, 2023City Council: Budget adjustments, Resolution 23-02 (public hearing)

In brief

Second Dam sediment removal appears on 5 recorded agendas, from the City Council meeting of February 7, 2023 to the City Council meeting of January 16, 2024.

On record, it was approved 3 times.

The most recent decision was approved (4-0) at the City Council meeting of January 16, 2024.

Follow the money and project delivery

Second Dam sediment removal

Approved

  1. Council action

    Approved according to the dated project source. Record → · Jan. 16, 2024

  2. Money in the record

    budget: $1.40 million — Second Dam sediment removal; budget: $400,000 — Hydro penstock repair; budget: $11,535 — K9 training seminar; budget: $23,900 — Employee benefit changes Record → · Jan. 16, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. January 16, 2024 · City Council

    Budget adjustments, Resolution 24-02 (public hearing)

    Approved · 4-0

    The council appropriated $11,535 for a K9 training seminar, $400,000 for hydro penstock repair, $23,900 for employee benefit changes and $1,400,000 for Second Dam sediment removal. Council Member Simmonds confirmed the sediment money covers extra material from last year's spring runoff.

    Moved by Council Member Mark Anderson, seconded by Council Member Jeannie Simmonds. Vote: 4-0; Council Member Ernesto López absent

  2. January 2, 2024 · City Council

    Workshop: budget adjustments, Resolution 24-02

    Discussed

    Finance Director Richard Anderson previewed $11,535 for a K9 training seminar, $400,000 to repair the hydro penstock damaged by an off-road driver, $23,900 for employee benefit changes and an additional $1,400,000 for Second Dam sediment removal, since a survey now shows 35,000 cubic yards rather than 14,000. The competing bid was nearly $6 million for 14,000 cubic yards. The electric fund would fall below its reserve target, with other funds able to cover it. Action was set for January 16.

  3. October 17, 2023 · City Council

    Budget adjustments, Resolution 23-43 (public hearing)

    Approved · 5-0

    The council appropriated $13,464 in CDBG funds, $8,080 for the library's interlibrary loan program and $1,000,000 from electric fund reserves for Second Dam sediment removal. Dr. Gail Yost asked about timing and community effects; Council Member Simmonds said most work would not affect the roadway, and the mayor said the contract was expected to start in December pending state and federal permits.

    Moved by Council Member Mark Anderson, seconded by Council Member Jeannie Simmonds. Vote: 5-0 on roll call

  4. October 3, 2023 · City Council

    Workshop: budget adjustments, Resolution 23-43

    Discussed

    Previewed $13,464 in additional HUD CDBG funding, $8,080 in state funds for the library's interlibrary loan program and $1,000,000 from electric fund reserves for Second Dam sediment removal. Light & Power Director Mark Montgomery said two bids were received, $5.7 million and $899,000, and staff selected the lower bid from a national firm with sediment-removal expertise. This year's runoff kept the hydro units from running because sediment clogged the screens; the sediment belongs to the Forest Service and permits were expected before work begins.

  5. February 7, 2023 · City Council

    Budget adjustments, Resolution 23-02 (public hearing)

    Approved · 5-0

    The council appropriated $75,977 for a subscription contract for ESRI services and $1,000,000 from electric fund reserves for sediment removal at Second Dam. Light and Power Director Mark Montgomery said removal could happen this year if permits allow, or may wait until next winter. No one spoke.

    Moved by Council Member Jeannie Simmonds, seconded by Council Member Mark Anderson. Vote: 5-0; the minutes say the motion carried unanimously, counted here as the 5 council members present