Main Street pedestrian underpass

Pedestrian underpass beneath Main Street at about 600 South, built with UDOT by ACME Construction. Construction was scheduled for summer 2025 with lane restrictions on Main Street and completion in late October or early November; the city later budgeted $275,000 in RAPZ funds toward it.

Where it stands
Under construction
Type
Public project
Location
Main Street near 600 South
Applicant
City of Logan with UDOT

Every hearing and vote

  1. June 3, 2025 · City Council

    Main Street pedestrian underpass update

    Discussed

    Public Works Director Paul Lindhardt said the underpass near 600 South is built with UDOT, with ACME Construction as contractor and Stanley Consultants overseeing. Box delivery is expected the first week of September. Main Street will close to one lane each way for up to 60 days, with up to 10 nights of full closure, and completion is expected in late October or early November. Chair Simmonds asked for advance signage near the Logan River Golf Course or at 100 West, and Lindhardt said the contractor must provide traffic control.

  2. July 15, 2025 · City Council

    Workshop: budget adjustments, Resolution 25-32

    Discussed

    Anderson previewed $150,000 from risk management reserves for anticipated Canyon Road Trail litigation and $159,276 in RAPZ-related items; the listed components (a $35,000 aquatic center boiler, $53,915 and $83,758 for disc golf and restrooms, and $275,000 for the Main Street underpass) total $447,673, and the minutes do not explain the difference. Mayor Daines said outside counsel was hired; the formal complaint is still in draft. Action was set for August 5.

  3. August 5, 2025 · City Council

    Budget adjustments, Resolution 25-32 (public hearing)

    Approved · 4-0

    The council appropriated $150,000 from risk management reserves for anticipated Canyon Road Trail litigation and $159,276 from the 2026 RAPZ municipal population allocation. The listed RAPZ components ($35,000 aquatic center boiler, $53,915 and $83,758 for disc golf, $275,000 for the Main Street underpass) total $447,673, and the minutes do not explain the difference. Council Member Mark Anderson thanked the mayor and city attorney for negotiating before litigation; Simmonds said more funding may be needed. Gail Yost praised the disc golf course.

    Moved by Council Member Jeannie Simmonds, seconded by Council Member Mark Anderson. Vote: 4-0; Council Member Amy Anderson excused

  4. December 2, 2025 · City Council

    RAPZ projects update

    Discussed

    Parks and Recreation Director Russ Akina said RAPZ funds run $400,000 to $440,000 a year across nine projects, including the outdoor recreation complex parking, the Middle Canal trail culvert, Maple View Park playgrounds, the Trapper Park bridge (installation December 8-18), an aquatic center boiler, a disc golf pavilion and the Main Street underpass at 600 South, due in spring.

  5. May 26, 2026 · City Council work session

    Public Works budget

    Discussed

    Director Paul Lindhardt and Sam Odd said the 1250 North and 200 East signal is live, the Main Street underpass is two weeks ahead of schedule, and the Thrushwood Bridge on 100 North goes to bid this fall at just under $8 million with $1.2 million requested. The 400 North and 600 West intersection needs $3.2 million, which with prior funds and a new $5.8 million county COG grant reaches a $12 million target. A 200 East corridor study is budgeted at $150,000.