North Logan's fiscal 2025 audit received a clean opinion, while its governmental funds spent down $8.1 million as construction, including the community center, drew on savings. This series follows the city's water borrowing, construction accounts, 2026 tax increase, audit follow-up and redevelopment agency, one public record at a time.
The North Logan City Council voted 5–0 on Aug. 5, 2026 to adopt a fiscal 2027 budget with property tax increases for general operations and the library, which the city put at 7.89% above the certified rate and $139,615 a year.
The North Logan City Council voted 5–0 on Aug. 5, 2026 to adopt a fiscal 2027 budget with property tax increases for general operations and the library, which the city put at 7.89% above the certified rate and $139,615 a year.
AI-generated illustration: The Utah Ledger · Original graphic · The Utah Ledger
North Logan's one fiscal 2025 audit finding was that the city could not document its fraud risk assessment. The council formally created an audit committee in October 2025, and the city's 2026 self-assessment scores 375 of 395 points.
AI-generated illustration: The Utah Ledger · Original graphic · The Utah Ledger
North Logan's Redevelopment Agency took in $669,492 in dedicated property taxes in fiscal 2025 and ended the year with $2,884,578. Staff told the board in June 2026 that several businesses are locating in a community reinvestment area, with revenue estimates expected after December.
AI-generated illustration: The Utah Ledger · Original graphic · The Utah Ledger
North Logan's Local Building Authority spent $6,424,234 on capital outlay in fiscal 2025, leaving its fund balance at $23,265. A separate capital projects fund recorded $1,653,950 for the community center building, and the city budgeted $4.3 million more on that line for fiscal 2026.
AI-generated illustration: The Utah Ledger · Original graphic · The Utah Ledger
In August 2024 the council authorized water revenue bonds for a state-funded loan of $8,030,000 at 2.25% to pay for tanks, a transmission line and a well. The loan does not appear in the city's June 2025 debt schedule, and the fiscal 2027 budget sets aside $159,091 for water bond principal.