Highland: library tax, consulting contract and trail change order

The Ledger's review of Highland's budgets, audits, debt and redevelopment money.

Living article · updated · 4 updates, newest first

The full audit section: stories by subject, key figures and records →

Background

Auditing Highland: what city records show about its audit, reserves, debt and 2026 budget

The Ledger is reviewing Highland's public financial records, starting with the fiscal 2025 audit, the fiscal 2027 budget and library tax increase, a renewed grant and legislative consulting contract, the Mitchell Hollow Trail and a state grant for secondary water meters. Every figure comes from a linked public record.

Read the explainer →

Latest update · September 1, 2026 · published Oct 16

Highland council trims Mitchell Hollow Trail change order to $148,084

Highland's council added up to $15,000 for trail construction engineering on Sept. 1, then voted 5-0 on Oct. 6 to approve a Vancon change order of up to $148,083.65, negotiated down from $160,129.20. A September register lists a separate $282,515.75 payment to the contractor.

4 stories since August 11, 2026

Timeline, newest first

  1. Highland council trims Mitchell Hollow Trail change order to $148,084 · published Oct 16
  2. Highland renews its $100,000 grant and legislative consulting contract on a 4–1 vote · published Oct 16
  3. State board amends Highland's $5 million meter grant as estimate falls to $9.15 million · published Oct 16
  4. Highland raises its library property tax, adding $172,488 a year to the library budget · published Oct 16