Cedar City: arena, wells and road contract costs

The Ledger's review of Cedar City's budgets, audits, debt and redevelopment money.

Living article · updated · 4 updates, newest first

The full audit section: stories by subject, key figures and records →

Background

Auditing Cedar City: what the city's own records say about its money

A facts-only review of Cedar City's finances, starting with the fiscal 2026-27 budget the City Council adopted in June, its new reserve policy and the contracts on its October agendas.

Read the explainer →

Latest update · October 14, 2026 · published Oct 16

Cedar City's new reserve policy: targets by fund, two descriptions of the 25% floor

Cedar City's fund balance and reserve policy sets a general fund floor, a capital fund target and an enterprise fund standard. The Sept. 16 staff report and the policy text describe the general fund floor on different bases, and the adoption vote appears so far only in draft minutes.

4 stories since October 14, 2026

Timeline, newest first

  1. Cedar City's new reserve policy: targets by fund, two descriptions of the 25% floor · published Oct 16
  2. 100 East roadway: final change order adds $117,500.05 to a $900,214.85 contract · published Oct 16
  3. Quichapa wells: Oct. 14 agenda lists second contract for Grimshaw Drilling at $801,365 · published Oct 16
  4. Cross Hollow covered arena: staff lists $1,022,062 in costs against $1,004,119 available · published Oct 16

Latest updates