Rocky Mountain Power North Orem transmission line rebuild

Rocky Mountain Power is rebuilding about 5 miles of transmission line through Orem to add capacity for system growth, replacing poles along roadways with traffic shifted rather than closed. Completion was targeted for the end of May 2021.

Where it stands
In review
Type
Public project
Location
1600 North, west of I-15 to the foothills, then south to Spanish Fork substation
Applicant
Rocky Mountain Power

Every hearing and vote

  1. January 26, 2021 · City Council

    Work session: Rocky Mountain Power North Orem transmission line rebuild

    Discussed

    Rocky Mountain Power staff said about 5 miles of line need to be rebuilt because of system growth. The route runs west of the freeway along 1600 North, east to the foothills, then south to the Spanish Fork substation. An outside contractor will change out poles along roadways, shifting traffic rather than closing roads, and work on busy roads in early mornings. Completion is expected by the end of May. Council members asked about coordination with road, water and trail projects.

    • Presenters: Rocky Mountain Power staff
    • Timeline: build done by end of May 2021