Orem development tracker

Rocky Mountain Power North Orem transmission line rebuild

Rocky Mountain Power is rebuilding about 5 miles of transmission line through Orem to add capacity for system growth, replacing poles along roadways with traffic shifted rather than closed. Completion was targeted for the end of May 2021.

In review

Type
Public project
Applicant
Rocky Mountain Power
Location
1600 North, west of I-15 to the foothills, then south to Spanish Fork substation

In brief

Rocky Mountain Power North Orem transmission line rebuild appears on one recorded agenda: the City Council meeting of January 26, 2021.

Follow the money and project delivery

Rocky Mountain Power North Orem transmission line rebuild

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. January 26, 2021 · City Council

    Work session: Rocky Mountain Power North Orem transmission line rebuild

    Discussed

    Rocky Mountain Power staff said about 5 miles of line need to be rebuilt because of system growth. The route runs west of the freeway along 1600 North, east to the foothills, then south to the Spanish Fork substation. An outside contractor will change out poles along roadways, shifting traffic rather than closing roads, and work on busy roads in early mornings. Completion is expected by the end of May. Council members asked about coordination with road, water and trail projects.

    • Presenters: Rocky Mountain Power staff
    • Timeline: build done by end of May 2021