New Orem City Hall

A new City Hall designed by Method Studios with Layton Construction as general contractor, to be designed before bidding, with construction planned to begin in March 2023.

Where it stands
In review
Type
Public project
Location
56 North State Street, Orem
Applicant
City of Orem

Every hearing and vote

  1. April 26, 2022 · City Council

    New City Hall design options (work session)

    Discussed

    Method Studios presented layout options. Staff said relocating operations during construction on the current footprint could cost over $2.4 million. The council said it prefers building the new City Hall separately from the current one and keeping as many trees as possible.

  2. May 10, 2022 · City Council

    New City Hall contractor (work session)

    Discussed

    City Manager Jamie Davidson said Layton Construction was selected as general contractor for the new City Hall.

  3. May 24, 2022 · City Council

    City manager update: City Hall timeline

    Discussed

    City Manager Jamie Davidson said the city will design the new City Hall with Method Studios and Layton Construction before bidding it out, with construction planned for March 2023. An asbestos review of the current building has begun. He also discussed the water tank at 400 South and 400 West.