Automated water meters (AMI)
Citywide automated metering project costing $7.3 million, with a $1.5 million grant and no bonds; customer portal rollout planned in early 2024.
- Where it stands
- Approved
- Type
- Public project
- Location
- Citywide
Every hearing and vote
February 13, 2024 · City Council
Automated water meter (AMI) rollout (work session)
Discussed
Public Works reported meters are installed (about 22,330 residential and 1,300 commercial) and the MyWater portal will reach all customers within four months, starting with 1,000 residents in each quadrant. The project cost $7.3 million, including a $1.5 million grant, with no bonds.