Orem development tracker

Automated water meters (AMI)

Citywide automated metering project costing $7.3 million, with a $1.5 million grant and no bonds; customer portal rollout planned in early 2024.

Where it stands
Approved
Type
Public project
Location
Citywide

Every hearing and vote

  1. February 13, 2024 · City Council

    Automated water meter (AMI) rollout (work session)

    Discussed

    Public Works reported meters are installed (about 22,330 residential and 1,300 commercial) and the MyWater portal will reach all customers within four months, starting with 1,000 residents in each quadrant. The project cost $7.3 million, including a $1.5 million grant, with no bonds.