Lehi development tracker

Data center code amendment

Proposed addition of data centers to the nonresidential use table and definitions. The council tabled it in October 2024 to study conditional use status, dedicated districts, noise studies and utility impacts.

Tabled

Type
Code change
Location
Citywide

In brief

Data center code amendment appears on one recorded agenda: the City Council meeting of October 8, 2024.

On record, it was tabled once.

The most recent decision was tabled (5-0) at the City Council meeting of October 8, 2024.

Follow the money and project delivery

Data center code amendment

Tabled

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 8, 2024 · City Council

    Ordinance 60-2024: adding data centers to the use table and definitions

    Tabled · 5-0

    After extended discussion of power and water use, noise and appropriate zoning districts, the council tabled the ordinance. Council Member Michelle Stallings asked staff to consider making data centers a conditional use, creating specific data center districts, requiring more thorough noise studies and mitigation, adding protections for adjacent residential areas and reviewing utility impact requirements.

    Moved by Council Member Michelle Stallings, seconded by Council Member Paige Albrecht. Vote: 5-0, unanimous