Park City Heights affordable housing mitigation
Housing mitigation plan for the Park City Heights subdivision by Ivory Homes, which has completed 68 of 79 affordable units. In February 2025 the Housing Authority set March 2026 and December 2026 deadlines for the remaining attainable homes.
- Where it stands
- Under construction
- Type
- Development agreement
- Location
- Park City Heights
- Homes
- 79
- Applicant
- Ivory Homes
Every hearing and vote
February 6, 2025 · City Council
Housing Authority: Park City Heights housing mitigation plan amendment
Approved with conditions · 4-0
Ivory Homes asked to extend the deadline for the remaining affordable units from the end of 2025 to the end of 2026 and to raise the attainable home price to $665,715. 68 of 79 affordable units are complete. Council Members Dickey and Parigian did not want a price increase. The Housing Authority approved completing phase four attainable units by March 30, 2026 and phase five by December 2026; the motion did not address price.
- Developer: Ivory Homes
- Affordable units complete: 68 of 79
November 6, 2025 · City Council
Consent: public improvement agreements, playground design and pickleball MOU extension
Approved · 5-0
Approved amendments to public improvement agreements for Park City Heights and Studio Crossing, a playground design contract of up to $4,000 and a 90-day extension to February 11, 2026 of the Wadsworth pickleball facility memorandum of understanding.
November 18, 2025 · City Council
Consent: acceptance of public improvements, Park City Heights Phase 4 (Ordinance 2025-22)
Approved · 5-0
Accepted public improvements for Park City Heights Phase 4.