Salt Lake City development tracker

Glendale Regional Park

Regional park project; Budget Amendment No. 4 (adopted Dec. 13, 2022) included $4.35 million in parks impact fees for phase one.

Approved

Type
Public project
Location
Glendale neighborhood, Salt Lake City
  1. Dec 13, 2022City Council: Budget Amendment No. 4, fiscal year 2022-23
  2. Dec 6, 2022City Council: Budget Amendment No. 4, fiscal year 2022-23 (hearing)
  3. Dec 6, 2022City Council work session: Budget Amendment No. 4, fiscal year 2022-23 follow-up
  4. Oct 4, 2022City Council work session: Glendale Regional Park Master Plan

In brief

Glendale Regional Park appears on 4 recorded agendas, from the City Council work session meeting of October 4, 2022 to the City Council meeting of December 13, 2022.

On record, it was approved once.

The most recent decision was approved (6-0) at the City Council meeting of December 13, 2022.

Follow the money and project delivery

Glendale Regional Park

Approved

  1. Council action

    Approved: Budget Amendment No. 4, fiscal year 2022-23 · Approved minutes Record → · Dec. 13, 2022

  2. Money in the record

    budget: $4.35 million — Glendale Regional Park phase one; bond: $24.2 million — Sales Tax Revenue Bonds, Series 2022 C (federally taxable); bond: $45.0 million — Sales Tax Revenue Bonds, Series 2022 B (non-taxable); bond: $23.5 million — General Obligation Series 2022 Streets Bonds, last issuance; grant: $5.00 million — Emergency Rental Assistance Program; budget: $2.54 million — Police patrol overtime; land: $3.57 million — Real property purchase (item I-3) Record → · Dec. 13, 2022

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. December 13, 2022 · City Council

    Budget Amendment No. 4, fiscal year 2022-23

    Approved · 6-0

    The Council adopted Ordinance 80 of 2022 amending the FY2022-23 budget for the items on the motion sheet, 6-0. Items include $38,509 for elections awareness, $490,847 in re-scoped homelessness funds, $500,000 for Dee Glen tennis courts, $4.35 million in parks impact fees for Glendale Regional Park phase one, $678,462 for two police substations, $750,000 for fire station gender-equity renovations, $430,000 and $3,567,564 for real property purchases, $2,539,019 in police patrol overtime, $24.24 million and $44.997 million in sales tax revenue bond proceeds, $23.49 million in general obligation streets bond proceeds, $694,122 in state shelter-cities grants, $260,687 for dam rehabilitation planning, $5 million in emergency rental assistance, $1.664 million in ARPA funds for the Clean Neighborhoods Team and a $10,000 pilot for RV wastewater disposal vouchers. Separate 6-0 motions approved two contract development specialists in Finance ($103,900 General Fund and $5,000 IMS Fund), one Public Services senior project manager ($133,000) and two Public Lands planners ($169,600). Council staff noted the motions did not include the seven staffing positions in the amendment and reviewed them.

    Moved by Council Member Wharton, seconded by Council Member Petro. Vote: 6-0

  2. December 6, 2022 · City Council

    Budget Amendment No. 4, fiscal year 2022-23 (hearing)

    No action · 6-0

    The Council held a hearing on the amendment to the FY2022-23 budget, which includes sales tax revenue bond funds for infrastructure and historic City properties, funding for phase one of Glendale Regional Park, police overtime, fire station renovations and emergency rental assistance. There was no public comment; action was deferred.

    Moved by Council Member Fowler, seconded by Council Member Valdemoros to close the hearing and defer action. Vote: 6-0

  3. December 6, 2022 · City Council work session

    Budget Amendment No. 4, fiscal year 2022-23 follow-up

    Discussed

    Third briefing before the evening's hearing. Staff described a remaining $10,000 pilot giving RV owners vouchers to dispose of wastewater at designated sites instead of the Jordan River, and six new full-time employees (four in Public Lands, two in Finance). Item A-5, $4.35 million in parks impact fees for Glendale Regional Park phase one, had been planned for withdrawal after the parks bond passed, but Council Members said they no longer wished to withdraw it and wanted to modify it. Staff said the park must be built by 2024 and bond-funded review timelines would not allow that. Other items discussed included $38,509 for election awareness, $490,847 in re-scoped homelessness funds and $500,000 for Dee Glen tennis courts.

  4. October 4, 2022 · City Council work session

    Glendale Regional Park Master Plan

    Discussed

    The Public Lands Department presented a preferred site plan for the former Glendale Water Park site, including an outdoor pool, climbing features, a skate park, flexible event spaces and a community plaza. Phase I is targeted for April 2024 with $3.2 million in funding, and the plan is scheduled for Planning Commission review this fall and Council adoption in December. Council Member Fowler said ongoing maintenance costs were not in the presentation and asked about programming; staff said the plan is to use Funding Our Future dollars for maintenance of new bond-funded facilities and return to the Council for added positions. Council Member Puy thanked staff for west-side engagement.