Salt Lake City development tracker

Glendale Park construction

Park construction estimated at $45 to $50 million with about $2.8 million in contingency, reviewed in the Capital Improvement Program briefing on August 18, 2026.

In review

Type
Public project
Location
Glendale Park
Applicant
Salt Lake City Public Lands
  1. Aug 18, 2026City Council work session: Capital Improvement Program follow-up
  2. Sep 17, 2024City Council work session: Glendale Park progress update

In brief

Glendale Park construction appears on 2 recorded agendas, from the City Council work session meeting of September 17, 2024 to the City Council work session meeting of August 18, 2026.

Follow the money and project delivery

Glendale Park construction

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    budget: $568,000 — New park restroom (CIP item 31) Record → · Aug. 18, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. August 18, 2026 · City Council work session

    Capital Improvement Program follow-up

    Discussed

    Kate Werrett reviewed the remaining funding log items. Members discussed funding a new park restroom while a citywide restroom study is pending, reallocating money to plant more trees, possible savings from phasing Glendale Park sport court lighting (about $500,000 for pickleball or tennis courts), Glendale Park's roughly $2.8 million construction contingency on an estimated $45 to $50 million build, and bike racks. Straw polls: unanimous support for paying for a West Temple and Mead Avenue crosswalk with flashing beacons from the Vision Zero line; 5-2 to pause the $568,000 new restroom item and consider reallocating it (Dugan and Wharton opposed); and a separate poll to fully fund it failed 4-3 (for: Dugan, Carlsen, Petro, Wharton). Council Member Puy asked for the cost of the administration's planting of 1,000 trees on the westside.

  2. September 17, 2024 · City Council work session

    Glendale Park progress update

    Discussed

    Public Lands updated Council on the new Glendale park, part of which must open to active use. Council Member Puy spoke about the westside pickleball community's frustration at the lack of courts. Staff said a safety and security plan for Phase II would be put in place when Phase I opens, and described a Strategic Capital Acquisition and Asset Management Plan to schedule projects and maintenance. Council Member Lopez Chavez asked that every project tie to the urban forest.