Salt Lake City development tracker

600 North / 700 North reconstruction

Corridor reconstruction and transformation project; Budget Amendment No. 3 added $3,204,371 in transportation impact fees.

In review

Type
Road project
Location
600 North and 700 North
  1. Sep 22, 2026City Council work session: Briefing: 600 and 700 North transportation project status
  2. Jan 16, 2024City Council work session: Budget Amendment No. 3, fiscal 2023-24 (follow-up)

In brief

600 North / 700 North reconstruction appears on 2 recorded agendas, from the City Council work session meeting of January 16, 2024 to the City Council work session meeting of September 22, 2026.

The most recent agenda collected for it, the City Council work session meeting of September 22, 2026, listed it with no result recorded.

Follow the money and project delivery

600 North / 700 North reconstruction

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    budget: $3.32 million — Additional funding, 2100 South reconstruction in Sugar House; budget: $3.20 million — Additional funding, 600/700 North reconstruction; budget: $400,000 — Security access control system upgrades; purchase: $135,993 — Downtown parking pay station replacements; budget: $500,000 — Police overtime for sanctioned campground pilot; contract: $250,000 — Consulting for enterprise billing systems Record → · Jan. 16, 2024

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 22, 2026 · City Council work session

    Briefing: 600 and 700 North transportation project status

    Pending

    Community and Neighborhoods was to brief the Council on the status, timeline and details of the 600 and 700 North transportation project.

  2. January 16, 2024 · City Council work session

    Budget Amendment No. 3, fiscal 2023-24 (follow-up)

    Discussed

    Finance staff gave a revenue update, noting $30 million was one-time savings and that vacancy rates showed departments trying to keep employees. Staff reviewed items A-2 through A-14, including $3,323,950 in transportation impact fees for 2100 South reconstruction in Sugar House (A-5), $3,204,371 for the 600/700 North reconstruction (A-6), $400,000 for security access control upgrades, $200,000 for road markings maintenance, $135,993 for downtown parking pay stations (A-10), $205,000 to re-appropriate for rail spur removal, $500,000 in unused ARPA funds for police overtime tied to the sanctioned campground pilot, $250,000 for enterprise billing consulting and two grants-related positions. Straw polls supported A-5 with a left turn from the property remaining on Douglas Street, and separating A-10 until more information on kiosk versus phone-app use was gathered; both were supported by all members present. Staff could not immediately answer questions on the rail spur contract and agreed to send information.