Wall Avenue Corridor Plan
Planning for the downtown section of Wall Avenue. The preferred concept is traffic calming with a landscaped median and shared-use path. Council consideration was extended in October 2025 for UDOT consultation, with resubmission expected in about six months.
- Where it stands
- In review
- Type
- Road project
- Location
- Wall Avenue, 22nd to 27th Streets
- Applicant
- Ogden City Planning Division
Every hearing and vote
November 18, 2025 · City Council
Wall Avenue Corridor Study preferred alternative: communications plan
No action
Because the item was extended on Oct. 21 so the administration could consult stakeholders such as UDOT, Council staff presented a communications plan. The preferred downtown concept (22nd to 27th streets) is traffic calming with a landscaped median and shared-use path, recommended unanimously by the Planning Commission on June 4, 2025. Council staff asked Planning to resubmit in about six months.