Pioneer Park stormwater detention basin
A stormwater detention basin and check dams at Pioneer Park funded mostly through the NRCS Emergency Watershed Protection program on a 75 percent federal, 25 percent city match. The council's Oct. 28, 2026 agenda asked it to ratify a request for $371,666.75 in additional federal funds and a four-month extension to Nov. 5, 2027; the project total is $591,516.40.
- Where it stands
- In review
- Type
- Public project
- Location
- Pioneer Park
- Applicant
- Price City
- Next hearing
- City Council, Wed, Oct 28
Follow the money and project delivery
Pioneer Park stormwater detention basin
- Council action
No approval or denial linked in the records collected.
- Money in the record
No itemized amount linked in the records collected.
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
October 28, 2026 · City Council
Pioneer Park stormwater detention basin: additional federal funding request
Pending
The council was asked to ratify a request to the Natural Resources Conservation Service for $371,666.75 more in Emergency Watershed Protection money for the basin. Price's match plus costs for required piping that the program does not cover total $219,849.65, for a project total of $591,516.40. The request also asks for a four-month extension to Nov. 5, 2027.