Contracts and spending
Who Price pays, for what, and how the vendor was chosen: the contracts, bid awards, change orders, purchases, grants and land deals recorded in the City Council meetings written up so far, from the meeting minutes and packets.
- Contracts, purchases and land deals approved in these meetings
- $0
- Line items
- 6
- Vendors
- 0
Recorded spending decisions and proposals
| Date | Who and what | Amount |
|---|---|---|
| Wed, Oct 28 | Natural Resources Conservation Service: Additional Emergency Watershed Protection funding for the Pioneer Park stormwater detention basin | $371,666.75 |
| Wed, Oct 28 | No vendor named: Price City match plus EWP-ineligible cost of required piping | $219,849.65 |
| Wed, Oct 28 | Utah Main Street program: Downtown District administration and nonprofit formation | $7,500 |
| Wed, Oct 28 | No vendor named: Water line easement for replacement and maintenance of the spring water transmission line | $5,000 |
| Wed, Oct 28 | Utah Associated Municipal Power Systems (UAMPS): Battery project UAMPS would own and finance with bonds, with Price paying all costs. UAMPS's presentation gives a quoted price of $10.52 million, $5.26 million after a 50 percent federal tax credit, and about $548,000 a year over 20 years | — |
| Wed, Oct 28 | Larson & Company: Financial and single audit services for the fiscal year ending June 30, 2026 | — |