Dry Creek improvements

A flood-control project on Dry Creek covered by an agreement with Salt Lake County Flood Control. On April 7, 2020 the council approved an amendment adding a $250,000 reimbursement.

Where it stands
Approved
Type
Public project
Location
Dry Creek, Sandy
Applicant
Sandy Public Utilities / Salt Lake County Flood Control

Every hearing and vote

  1. April 7, 2020 · City Council

    Flood control agreement amendments for Dry Creek and Sandy Canal Trail (Resolutions 20-09C and 20-08C)

    Approved · 7-0

    Resolution 20-09C amends the agreement with Salt Lake County Flood Control for an additional $250,000 reimbursement for the Dry Creek Improvements project. Resolution 20-08C amends the Storm Drainage and Flood Control Agreement for an additional $50,000 for the Sandy Canal Trail project and relieves Sandy Public Utilities and county Flood Control of future liability and expense in that right-of-way corridor. Both were adopted on the consent calendar.

    Moved by Council Member Kris Coleman-Nicholl, seconded by Council Member Brooke Christensen. Vote: 7-0 (consent calendar)

  2. July 11, 2023 · City Council work session

    Interlocal agreement for 300 West and Dry Creek culvert in South Jordan

    Discussed

    Chief Public Utilities Engineer Tyler Shelley presented an agreement to replace the Dry Creek culvert, sized for 100-year storm flows, to reduce flood risk in Sandy and South Jordan. Council members supported it and planned to vote at the next business session. The notes give no cost.

  3. July 18, 2023 · City Council

    Interlocal agreement for road improvements along 300 West and the Dry Creek channel in South Jordan (Resolution 23-31C)

    Approved

    Public Utilities presented the interlocal agreement; it was approved on the consent calendar. The notes give no cost.