Village zone power line burial
A developer proposed splitting the roughly $130,000 cost of burying the last overhead lines in the village zone; on September 5, 2024 the council indicated it did not support cost sharing.
Denied
- Type
- Public project
- City Council: Work meeting: power lines in the village
- City Council: Work meeting: underground power lines in the village zone
In brief
Village zone power line burial appears on 2 recorded agendas, from the City Council meeting of August 22, 2024 to the City Council meeting of September 5, 2024.
Follow the money and project delivery
Village zone power line burial
- Council action
No approval or denial linked in the records collected.
- Money in the record
budget: $65,000 — Requested city share of burying overhead power lines (total about $130,000) Record → · Aug. 22, 2024
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
September 5, 2024 · City Council
Work meeting: power lines in the village
No action
The council indicated it does not support cost sharing for burying power lines; no formal vote.
August 22, 2024 · City Council
Work meeting: underground power lines in the village zone
Discussed
A developer proposed splitting 50/50 the cost, about $130,000 in total, of burying the last overhead lines in the zone, asking the city for about $65,000 from the capital projects fund, which would need a budget amendment. Members raised precedent concerns and asked the engineer to confirm it is the last segment. No action.