Holladay development tracker

I-215 shared use path

Feasibility study with a regional grant of four alternatives ranging up to $17.2 million, presented October 5, 2023.

Where it stands
In review
Type
Public project

Every hearing and vote

  1. October 5, 2023 · City Council work session

    Work meeting: I-215 shared use path feasibility study

    Discussed

    Horrocks Engineers presented four alternatives, ranging from $1.2 million to $8.5 million for park-area segments and $9.9 million to $17.2 million in total, using a regional grant. The study drew 187 survey responses and 100 emails; two alternatives were preferred.