UAMPS Millard County peaker power contract

Power sales contract for a 200-megawatt gas peaker online in 2029 with a 26.25-megawatt Logan subscription at a stated $112 per megawatt-hour. The council approved it 5-0 on December 3, 2024.

Where it stands
Approved
Type
Public project
Location
Millard County, Utah
Applicant
UAMPS

Every hearing and vote

  1. November 19, 2024 · City Council

    Workshop: Millard County Power Project, Resolution 24-46

    Discussed

    Light & Power Director Mark Montgomery described a UAMPS power sales contract for a 200-megawatt gas peaker online in 2029 with a 26.25-megawatt subscription, a peaker cost of $93 to $167 per megawatt-hour and a city share of 26 to 31 percent of a roughly $700 million plant, plus a $5 million PacifiCorp study deposit. Action was set for December 3.

  2. December 3, 2024 · City Council

    Millard County peaker power contract, Resolution 24-46

    Approved · 5-0

    The council approved a UAMPS power sales contract for a 200-megawatt gas peaker online in 2029, with a 26.25-megawatt subscription at a stated $112 per megawatt-hour, about $10.3 million a year, and a $180,000 city obligation for transmission studies. Patrick Belmont, vice chair of the resource advisory board, asked for a continuance and favors renewables; Joshua Molitor asked for further consideration.

    Moved by Council Member Mike Johnson, seconded by Council Member Mark Anderson. Vote: 5-0 on roll call

  3. December 2, 2025 · City Council

    Energy update

    Discussed

    Light & Power Resource Manager Tyson Godfrey reported a 100-megawatt peak load and a power shortfall until April 2026, with the regional day-ahead market going live May 1, 2026. Over three months the mix was 18 percent renewable, 58 percent dispatchable and 25 percent market. Sunnyside coal (5 MW) is permanently offline at no city payment, the Nebo gas plant runs at half capacity until April, and a 10-megawatt Sub 9 generator is targeted for April 2026. New firm resources include Fremont Solar and battery (10 MW solar, 5 MW battery, by December 2027), Millard County peaking (26.25 MW) and Power County gas (15 MW, by 2031). Potential resources include 8 megawatts of lagoon solar, a Cache County solar and storage project denied zoning by the county, and 2 megawatts of geothermal.