Council agenda includes Corrigan Farms data center rezone, water and wastewater impact fee plans, archery and fencing code changes (agenda only)
October 6, 2026, 4:00 p.m. · Eagle Mountain City Council Chambers, 1650 E Stagecoach Run, Eagle Mountain, Utah
Based on the posted agenda; no minutes were available. After a 4 p.m. work session on RV parking, the fire authority, chaplain services and the investment portfolio, the 7 p.m. session lists a rezone and development agreement for Corrigan Farms to add the RTI overlay to a 41-acre parcel that could allow a data center with a natural gas power plant, updates to the culinary water and wastewater impact fee plans adding the Spring Run and Talons Cove area, code amendments on archery, fencing, residential standards and master site plans, the Ranches Parkway interlocal agreement with Utah County, a purchase agreement with Smith's Food and Drug Centers, a community garden policy, and speed study results. Outcomes are not known.
From the agenda; results are added when minutes are posted. Updated October 14, 2026.
Decisions at a glance
Agenda, item by item
Item 1.A-1.D · Other
Work session: RV parking code, UFA overview, chaplain services, investment portfolio
Pending
Discussion items listed on the agenda for the 4 p.m. work session.
Item 10 · Other
Consent agenda: bond releases (into warranty) for Firefly NPA 8, Harmony and Overland Village 2 plats, and minutes
Pending
Bond releases for Firefly NPA 8 Phase A Plat 9 and Phase B Plat 1, Harmony Phase A Plat 14, and Overland Village 2 Phase A Plats 4 and 5, plus minutes of September 15 and 24.
Item 12.A · Roads and utilities
Ranches Parkway improvement interlocal agreement with Utah County
Pending
Resolution on the consent agenda; no amount is listed.
- ContractAmount not given
Item 12.B · Contract
Purchase agreement with Smith's Food and Drug Centers, Inc.
Pending
Resolution on the consent agenda; the property and amount are not listed.
- PurchaseAmount not given to Smith's Food & Drug Centers, Inc.
Item 12.C · Contract
Purchase agreements for Utah County parcels 49:601:0079 and 49:601:0080 following a land disposal application in Pioneer Addition Phase II
Pending
Resolution on the consent agenda.
Item 12.D · Parks
Community garden policy
Pending
Resolution on the consent agenda.
Item 13.A-13.B · Other
Land disposal applications for portions of parcels at Silverlake Plat 29 and in Meadow Ranch plats (about 0.021 acre and 0.72 acre)
Pending
Resolutions to let two land disposal applications proceed, directing staff to begin notice and a public hearing.
Item 14.A · Zoning
Corrigan Farms rezone: add the RTI overlay zone to parcel 59:068:0006
Pending
Senior Planner David Stroud to present; the applicant seeks the overlay on a 41-acre parcel to potentially allow a data center with a natural gas power plant.
Item 14.B · Development
Corrigan Farms development agreement
Pending
City Attorney Marcus Draper to present an agreement setting development and infrastructure requirements for the data center.
Item 15.A · Taxes and fees
Culinary water impact fee facilities plan update
Pending
City Engineer Vince Hogge to add the Spring Run and Talons Cove area and update project cost estimates.
Item 15.B · Taxes and fees
Wastewater master plan and wastewater impact fee facilities plan update
Pending
City Engineer Vince Hogge to add the Spring Run and Talons Cove area and update cost estimates.
Item 15.C · City code
Archery use code, EMMC 9.10 and 17.47
Pending
Would allow outdoor archery ranges in the Outdoor Shooting Range Overlay Zone and indoor ranges as a special use, with standards meant to discourage backyard archery.
Item 15.D · City code
Fencing and screening code, EMMC 17.60.120
Pending
Would allow barbed wire fencing in the RTI overlay zone and bar barbed wire atop chain link in industrial areas except RTI.
Item 15.E · City code
Residential standards table, EMMC 17.25.040
Pending
Would treat existing lots under 4,500 square feet rezoned to RC, and existing smaller setbacks, as legally conforming.
Item 15.F · City code
Master site plans, EMMC 17.100.040
Pending
Would clarify when a master or standard site plan is required, require a separate plat application for subdivision within a site plan, and require master site plan approval before plat approval.
Item 16.A · Roads and utilities
Speed study results
Pending
Discussion only, about one hour.
What residents said
Data center with natural gas power plant at Corrigan Farms