Traffic calming and pedestrian safety improvements
Sidewalk gap fills, striping and bulb-out crosswalks on 100 West and near schools, with $200,000 in FY27 Transportation Tax funds. Staff proposes doing the work through a change order with the 300 South Trail contractor.
- Where it stands
- Proposed
- Type
- Road project
- Location
- 100 West; 910 South; Mill Road
Follow the money and project delivery
Traffic calming and pedestrian safety improvements
- Council action
No approval or denial linked in the records collected.
- Money in the record
change-order: $200,000 — Traffic calming and pedestrian safety improvements (budget figure, not a bid) Record → · Oct. 20, 2026
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
October 20, 2026 · City Council
Traffic calming and pedestrian safety improvements
Pending
Staff proposes striping and sidewalk gap fills on the west side of 100 West between 600 South and 1000 South (about 1,100 linear feet of 5-foot sidewalk), school crosswalks with bulb-outs at 910 South and 100 West and at 910 South and 300 West (the latter with pedestrian-activated flashing beacons), and bulb-outs near 640 North and 380 North Mill Road and near Willow Way and Valley Hills Drive. Street parking would be lost where bulb-outs and a turn lane go in. Staff proposes a change order with the contractor already building the 300 South Trail, whose bid was 12% below the next bidder and 27% below the average, and asks for an exception to the three-quote rule for change orders of this size.
- Staff recommendation: approve if agreeable terms are reached with existing contractors