Sandy development tracker

Centennial Parkway partial street vacation

Vacation of 29,276 square feet of Centennial Parkway between 10200 South and Mall Ring Road was adopted 7-0 as Ordinance 21-34 on Dec. 7, 2021 for a project that is no longer planned. On Sept. 29, 2026 the city attorney told the council it must re-dedicate the segment to keep it a public street; an ordinance dedicating it was on the Oct. 6, 2026 agenda.

Where it stands
Approved
Type
Road project
Location
Centennial Parkway between 10200 South and Mall Ring Road
Applicant
Not stated in the minutes notes

Every hearing and vote

  1. December 7, 2021 · City Council

    Centennial Parkway partial street vacation (Ordinance 21-34)

    Approved · 7-0

    Craig Evans presented the vacation of 29,276 square feet of Centennial Parkway between 10200 South and Mall Ring Road, including a traffic impact study; staff recommended approval. City Traffic Engineer Britney Ward discussed traffic effects. Steve Van Maren said he was disappointed that the parade route may need to change. The council adopted the ordinance 7-0.

    Moved by Council Member Kris Coleman-Nicholl, seconded by Council Member Brooke Christensen. Vote: 7-0

  2. September 29, 2026 · City Council

    Centennial Parkway street dedication

    Discussed

    City Attorney Lynn Pace explained that a 2021 ordinance vacated part of Centennial Parkway for a project that is no longer planned, and the council must re-dedicate the segment to keep it a public street. Information item; it returns for consideration.

  3. October 6, 2026 · City Council

    Ordinance dedicating a portion of Centennial Parkway between 10200 South and Mall Ring Road

    Pending

    Legistar lists the item as adopted; the motion and tally are not available because minutes are not yet posted.