Fiscal Year 2024-25 Capital Improvement Program
Project-specific funding allocations for the city's fiscal year 2025 capital improvement program, which covers construction, purchase or renovation of buildings, parks, streets and other city-owned structures. The council adopted Resolution 27 of 2024 on Aug. 27, 2024, 7-0.
Approved
- Type
- Public project
- Applicant
- Salt Lake City
- City Council: Resolution 27 of 2024: FY2024-25 Capital Improvement Program allocations
- City Council work session: Capital Improvement Program follow-up
- City Council: Fiscal Year 2024-25 Capital Improvement Program project funding hearing
In brief
Fiscal Year 2024-25 Capital Improvement Program appears on 3 recorded agendas, from the City Council meeting of August 13, 2024 to the City Council work session meeting of August 27, 2024.
On record, it was continued once and approved once.
The most recent decision was approved (7-0) at the City Council meeting of August 27, 2024.
Follow the money and project delivery
Fiscal Year 2024-25 Capital Improvement Program
- Council action
Approved according to the dated project source. Record → · Aug. 27, 2024
- Money in the record
No itemized amount linked in the records collected.
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
August 27, 2024 · City Council
Resolution 27 of 2024: FY2024-25 Capital Improvement Program allocations
Approved · 7-0
Council adopted the project-specific capital improvement funding allocations shown in the attached funding log, following the straw polls earlier in the day.
August 27, 2024 · City Council work session
Capital Improvement Program follow-up
Discussed
Ben Luedtke reviewed how to use the remaining $595,153. Council preferred to earmark security fencing for the International Peace Garden under the Jordan River revitalization item. At Council Member Lopez Chavez's request, with all present supporting, $30,000 of unallocated funds would go to banner arms on light poles on Harvey Milk Boulevard, and she asked staff to explore a special assessment area there. Council Member Petro asked to raise the art item to $200,000, an increase of $33,000, which all supported. About $52,000 would go to citywide safer crossings. Staff will draft contingency language requiring a management plan for the Green Loop.
August 13, 2024 · City Council
Fiscal Year 2024-25 Capital Improvement Program project funding hearing
Continued · 6-0
Council heard a final hearing on project-specific allocations in the Capital Improvement Program, which Council must approve by September 1. About ten speakers commented. Several asked for a mid-block crosswalk at 500 East, and four residents and a neighbor asked for lighting, curb and gutter on Fayette Avenue between 200 West and 240 West, citing parking and safety. Others supported Green Loop, Harvey Milk Boulevard and Memory Grove lighting projects, a park on 1000 West and open space on the west side, and noted the backlog of unfunded requests. Council closed the hearing; action was set for August 27.