700 South reconstruction

Reconstruction and realignment of 700 South, funded in part by a $611,000 Salt Lake County corridor preservation grant. The Council adopted Resolution 11 of 2021 approving the interlocal agreement on April 20, 2021; completion is expected in summer 2022.

Where it stands
Approved
Type
Road project
Location
700 South

Every hearing and vote

  1. April 13, 2021 · City Council work session

    Interlocal agreement for 700 South reconstruction corridor preservation funds

    Discussed

    Staff explained that Salt Lake County would provide a $611,000 grant for realigning 700 South, with project completion expected in summer 2022. The City Engineer described the roadway, the property purchased and the project history.

  2. April 20, 2021 · City Council

    Interlocal agreement for 700 South reconstruction corridor preservation funds

    Approved · 7-0

    The Council adopted Resolution 11 of 2021 authorizing the agreement with Salt Lake County for transfer of corridor preservation funds for the 700 South reconstruction.