Logan development tracker

Lloyd Estates Subdivision financial assurance

The city called $200,000 in a developer's financial assurance after required improvements, mainly a stormwater detention basin, went unfinished. The city will use contractors and engineering support to complete safety, ADA, retention basin and homeownership-related items first. The council appropriated the funds 4-0 on April 21, 2026.

Under construction

Type
Subdivision
Location
Lloyd Estates Subdivision, Logan
Applicant
Subdivision developer
  1. Apr 21, 2026City Council: Lloyd Estates financial assurance, Resolution 26-11 (public hearing)
  2. Apr 7, 2026City Council: Workshop: Lloyd Estates financial assurance, Resolution 26-11

In brief

Lloyd Estates Subdivision financial assurance appears on 2 recorded agendas, from the City Council meeting of April 7, 2026 to the City Council meeting of April 21, 2026.

On record, it was approved once.

The most recent decision was approved (4-0) at the City Council meeting of April 21, 2026.

Follow the money and project delivery

Lloyd Estates Subdivision financial assurance

Under construction

  1. Council action

    Approved: Lloyd Estates financial assurance, Resolution 26-11 (public hearing) · Approved minutes Record → · April 21, 2026

  2. Money in the record

    guarantee: $200,000 — Developer financial assurance for incomplete subdivision improvements Record → · April 21, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. April 21, 2026 · City Council

    Lloyd Estates financial assurance, Resolution 26-11 (public hearing)

    Approved · 4-0

    The council appropriated $200,000 in financial assurance called from the developer, to pay contractors and some engineering support given a vacant engineer position. City Engineer Darren Farar said the money will address the retention basin first and minor items like chipped concrete may not be finished if funds run short. Council Member Simmonds said homeowners should not receive less than expected, and Council Member López said delays are affecting mortgage qualification.

    Moved by Council Member Jeannie Simmonds, seconded by Council Member Ernesto López. Vote: 4-0; Council Member Melissa Dahle excused

  2. April 7, 2026 · City Council

    Workshop: Lloyd Estates financial assurance, Resolution 26-11

    Discussed

    Finance Director Richard Anderson previewed appropriating $200,000 in financial assurance funds called from the developer of the Lloyd Estates Subdivision, which did not complete required improvements, chiefly a stormwater detention basin. The bond is nearing expiration and may not cover the full cost. Staff called it the first such case in many years.