1200 East roundabouts

Roundabouts on 1200 East at 1000 North and 800 North, funded in part by $1,811,398 from the Cache Metropolitan Planning Organization appropriated in the spring 2023 budget adjustments.

Where it stands
Approved
Type
Road project
Location
1200 East at 1000 North and 800 North
Applicant
City of Logan

Every hearing and vote

  1. April 4, 2023 · City Council

    Workshop: budget adjustments, Resolution 23-08

    Discussed

    Staff previewed $1,811,398 from the Cache Metropolitan Planning Organization for roundabouts on 1200 East (at 1000 North and 800 North), a $5,321 state grant for fire EMS equipment and training, and $95,496 from the state for alcohol enforcement. Action was set for April 18.

  2. April 18, 2023 · City Council

    Budget adjustments, Resolution 23-08 (public hearing)

    Approved · 4-0

    The council appropriated $1,811,398 from the Cache Metropolitan Planning Organization for the 1200 East roundabouts, a $5,321 state grant for fire EMS equipment and training, and $95,496 in state funds for alcohol enforcement. No one spoke.

    Moved by Council Member Mark Anderson, seconded by Council Member Tom Jensen. Vote: 4-0 on roll call; López absent

  3. March 5, 2024 · City Council

    Capital projects update

    Discussed

    Public Works Director Paul Lindhardt listed a signal at 1000 North and 200 West, roundabouts on 1200 East between 750 North and 1100 North, sewer and waterline work on 200 North ahead of a UDOT overlay and the SR-30 project, reconstruction of 200 South from 1200 West to 1900 West for the Logan Outdoor Recreation Complex, CDBG waterline work at 300 South and 300 East, and replacement of six traffic signals.

  4. May 21, 2024 · City Council

    Workshop: budget adjustments, Resolution 24-17

    Discussed

    Previewed $1,225,000 for Utah State University's cost share of the 1200 East roundabout project and $23,206 in police overtime reimbursements. Public Works Director Paul Lindhardt said there are two roundabouts, near the tennis courts and the cemetery, the road closes May 28 and will not finish before the school year starts. Action was set for June 4.

  5. June 4, 2024 · City Council

    Budget adjustments, Resolution 24-17 (public hearing)

    Approved · 5-0

    The council appropriated $1,225,000 for Utah State University's cost share of the 1200 East roundabouts and $23,206 in police overtime reimbursements. Dr. Yost asked for roundabout education, especially for young drivers.

    Moved by Council Member Jeannie Simmonds, seconded by Council Member Mike Johnson. Vote: 5-0 on roll call