Spanish Fork development tracker

Cold Springs pipeline rehabilitation

Rehabilitation of one of the two pipelines that bring spring water down the canyon, including a crossing under the railroad. On Oct. 6, 2026 the council approved a $519,902.28 Phase 2 change order for railroad requirements and flagging; the contractor expected to finish the remaining work in about ten days.

Where it stands
Under construction
Type
Public project
Location
Cold Springs water transmission pipeline
Follow the money and project delivery

Cold Springs pipeline rehabilitation

Under construction

  1. Council action

    Approved: Cold Springs Pipeline Rehabilitation Phase 2 change order · Approved minutes Record → · Oct. 6, 2026

  2. Money in the record

    change-order: $519,902.28 — Railroad flagging and observation, filling the abandoned pipe under the railroad and a drain valve, Cold Springs Pipeline Rehabilitation Phase 2 Record → · Oct. 6, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 6, 2026 · City Council

    Cold Springs Pipeline Rehabilitation Phase 2 change order

    Approved · 5-0

    The council approved a $519,902.28 change order on the Cold Springs pipeline rehabilitation. About $144,000 covers railroad requirements to fill an abandoned pipe section under the railroad with flowable concrete and add a drain valve. The remaining estimate of about $376,000 is mainly additional railroad flagging and observation by RailPros. Public Works Director Cory Pierce said the figure is a conservative estimate and could come in lower.

    • The original bid included about $300,000 for railroad flagging and observation
    • The contractor was working five 12-hour days a week to shorten the railroad observation period
    • One of the two Cold Springs pipelines was out of service during rehabilitation; the contractor expected to finish the remaining work in about ten days

    Councilman Oyler moved; Councilman Marshall seconded.. Vote: 5-0 on roll call; Oyler, Cardon, Beck, Tooke and Marshall voting yes