Provo development tracker

Data center overlay zone

Citywide code changes on data centers. After an Aug. 19 direction to draft an overlay zone, the council on Sept. 23, 2025 removed data centers as permitted or conditional uses and enacted Chapter 14.34A creating a data center overlay zone, both 7-0.

Approved

Type
Code change
  1. Sep 23, 2025City Council: Removing data centers as permitted or conditional uses
  2. Sep 23, 2025City Council: Data center overlay zone, Chapter 14.34A
  3. Sep 23, 2025City Council work session: Removing data centers from permitted and conditional uses
  4. Sep 23, 2025City Council work session: Data center overlay zone, Chapter 14.34A
  5. Aug 19, 2025City Council work session: Data center policy and zoning

In brief

Data center overlay zone appears on 3 recorded agendas, from the City Council work session meeting of August 19, 2025 to the City Council work session meeting of September 23, 2025.

On record, it was approved 2 times.

The most recent decision was approved (7-0) at the City Council meeting of September 23, 2025.

The City Council work session meeting of September 23, 2025 gave staff direction on it; that was not a vote on the application itself.

Follow the money and project delivery

Data center overlay zone

Approved

  1. Council action

    Approved: Removing data centers as permitted or conditional uses · Agenda and reports Record → · Sept. 23, 2025

  2. Money in the record

    No itemized amount linked in the records collected.

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. September 23, 2025 · City Council

    Removing data centers as permitted or conditional uses

    Approved · 7-0

    The council approved a Title 14 amendment removing data centers as permitted or conditional uses (PLOTA20250458).

    Vote: 7-0

  2. September 23, 2025 · City Council

    Data center overlay zone, Chapter 14.34A

    Approved · 7-0

    The council enacted Chapter 14.34A creating a data center overlay zone (PLOTA20250182).

    Vote: 7-0

  3. September 23, 2025 · City Council work session

    Removing data centers from permitted and conditional uses

    Discussed

    Presentation of an ordinance amending Title 14 to remove data centers as permitted or conditional uses (PLOTA20250458), scheduled for that evening's council meeting.

  4. September 23, 2025 · City Council work session

    Data center overlay zone, Chapter 14.34A

    Approved · 7-0

    Council Member Becky Bogdin moved, seconded by Council Member Craig Christensen, to include the three Planning Commission recommendations and add language on water contamination mitigation strategies in the final ordinance. It passed 7-0, and the ordinance went to the evening council meeting.

    Moved by Council Member Becky Bogdin, seconded by Council Member Craig Christensen. Vote: 7-0

  5. August 19, 2025 · City Council work session

    Data center policy and zoning

    Approved · 7-0

    The council discussed data center policy and zoning considerations. Council Member Gary Garrett moved to ask staff to draft legislation leading to a data center overlay zone, seconded by Council Member Becky Bogdin. It passed 7-0.

    Moved by Council Member Gary Garrett, seconded by Council Member Becky Bogdin. Vote: 7-0