Suntran Transit Facility

A new transit facility with six maintenance bays under construction by Bonneville. A $663,239.24 change order for bay equipment was on the council's Oct. 22, 2026 agenda, funded from the Public Transit Fund with a state grant for the Zion route.

Where it stands
Under construction
Type
Public project
Follow the money and project delivery

Suntran Transit Facility

Under construction

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    change-order: $663,239.24 — Automotive equipment for six maintenance bays, Suntran Transit Facility Record → · Oct. 22, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 22, 2026 · City Council

    Suntran Transit Facility change order

    Pending

    The council was asked to approve a change order to the construction contract for the new Suntran Transit Facility. It adds automotive equipment for the six maintenance bays that is attached to the building or must be installed during construction.