Emigration Canyon development tracker

Emigration Canyon road improvement project

A road improvement design project with Phase 1 survey, utility mapping, environmental review and public involvement now scheduled through Jan. 15, 2027 under Contract Modification #3. Phase 2 final plans will be scoped after Phase 1.

In review

Type
Road project
Location
Emigration Canyon Road
Applicant
Greater Salt Lake Municipal Services District / UDOT
  1. Nov 2, 2026City Council: Road Improvement Project Contract Modification #3
  2. Oct 20, 2026City Council: Road improvement contract modification #3

In brief

Emigration Canyon road improvement project appears on 2 recorded agendas, from the City Council meeting of October 20, 2026 to the City Council meeting of November 2, 2026.

The most recent agenda collected for it, the City Council meeting of November 2, 2026, listed it with no result recorded.

Follow the money and project delivery

Emigration Canyon road improvement project

In review

  1. Council action

    No approval or denial linked in the records collected.

  2. Money in the record

    change-order: $239,746.69 — Contract Modification #3 cost estimate (not-to-exceed, cost plus fixed fee) Record → · Nov. 2, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. November 2, 2026 · City Council

    Road Improvement Project Contract Modification #3

    Pending

    Modifications #1 and #2 were date extensions. Modification #3 adds survey, utility mapping, a categorical exclusion, public involvement and preliminary design tasks. Phase 1 is to finish Jan. 15, 2027, after notice to proceed on Feb. 12, 2026 and earlier extensions of the scope completion date from April 2026 to August 2026 to April 30, 2027. Phase 2, final plans and construction documents, will be scoped after Phase 1 and city approval.

    • Phase 1 extended through Jan. 15, 2027
    • Phase 2 to be scoped after Phase 1
  2. October 20, 2026 · City Council

    Road improvement contract modification #3

    Pending

    Discussion and potential action on approving Contract Modification #3 for the road improvement project; the council held a special meeting on the item Nov. 2.