Emigration Canyon council holds special meeting on a road project contract change that adds nine months to the design phase
November 2, 2026, 10:00 a.m. · Zoom (virtual)
The Emigration Canyon Council met by Zoom on Nov. 2 for one item: approval of Contract Modification #3 for the road improvement project. The engineering scope says the modification adds work UDOT, the Greater Salt Lake Municipal Services District and the city asked for, including project management, preliminary roadway design, public involvement, environmental review and right-of-way boundaries, and extends Phase 1 by nine months through Jan. 15, 2027. The outcome was not yet posted.
From the agenda; results are added when minutes are posted. Updated November 3, 2026.
In brief
1 item came up for a decision or discussion: 1 pending.
The agenda records 1 dollar amount, the largest $239,746.69.
1 item here is tracked in the city's development tracker.
This write-up links 2 source documents.
Residents raised road project schedule.
The previous City Council meeting was on October 20, 2026: Emigration Canyon council agenda: WestConnect pipeline committee, special event penalty and road safety design guidelines
Decisions at a glance
| Item | Result |
|---|---|
| Road Improvement Project Contract Modification #3 | Pending |
Agenda, item by item
Item 2A · Roads and utilities
Road Improvement Project Contract Modification #3
Pending
Modifications #1 and #2 were date extensions. Modification #3 adds survey, utility mapping, a categorical exclusion, public involvement and preliminary design tasks. Phase 1 is to finish Jan. 15, 2027, after notice to proceed on Feb. 12, 2026 and earlier extensions of the scope completion date from April 2026 to August 2026 to April 30, 2027. Phase 2, final plans and construction documents, will be scoped after Phase 1 and city approval.
- Change order$239,746.69 to Avenue (consultant)
- Phase 1 extended through Jan. 15, 2027
- Phase 2 to be scoped after Phase 1
What residents said
Road project schedule