Local news, council decisions, projects and city spending, with links to the agendas, minutes and reporting behind each story.
Latest decisions
- Local Building Authority organization and lease revenue bond parameters resolutions, City Hall and Hogan Park project Approved · 6-0
- Resolution granting funds to the Bountiful Davis Art Center Approved · 6-0
- Fertilizer purchase for fiscal 2027 and consent agenda Approved · 6-0
Meetings and decisions, item by item →
Follow the money and what happened next
Trace the decisions and financial records linked to Woods Cross's projects. A budget, bond ceiling, contract authorization and actual payment describe different things.
Open questions in our reporting
- How Woods Cross picked its City Hall architect and construction manager
What the signed architect and construction-manager contracts provide. The Nov. 18 packet's drafts propose fee terms, and their signature lines are blank. The minutes state no fee amounts.
- Woods Cross awards $4.2 million water tank contract after low bid topped bond estimate
Whether the council formally adopted a $4,912,236 total not-to-exceed amount. The draft resolution in the packet proposes it, and the approved minutes record only the contract award.
- Woods Cross raised its property tax revenue by about $995,000 on a 3–2 vote
Why the Aug. 4 minutes record the certified rate as .0019016 and the revenue as "$994.249.00" and "$9994,249.00," figures that differ from the state's final listing. The Ledger has not reviewed the signed resolution.
Woods Cross: building authority bonds, tax revenue and water tank →

How Woods Cross picked its City Hall architect and construction manager
Woods Cross's council conditionally approved Method Studio as architect and Hogan Construction as construction manager for the new City Hall and Hogan Park in November 2025, after scoring and public interviews. Check registers from July through September 2026 list three payments to Method Studio.

Woods Cross awards $4.2 million water tank contract after low bid topped bond estimate
Woods Cross's council awarded Patriot Construction a $4,217,641.34 contract to replace the 1500 South water tank on Aug. 6, 2026. A month earlier, the low bid of $4,827,527 exceeded the project's $4,012,236 bond estimate, and the council agreed to shift $900,000 toward the tank.

Woods Cross raised its property tax revenue by about $995,000 on a 3–2 vote
Woods Cross's council voted 3–2 on Aug. 4, 2026 to adopt the fiscal 2027 budget and a higher 2026 property tax rate. The city's notice put the increase at $995,285 a year, 46.86% over the prior year's budgeted property tax revenue, and the budget dedicates that amount to new City Hall debt service.

Woods Cross building authority proposes up to $33 million in bonds for City Hall and park
A notice posted Oct. 7 says Woods Cross's new Local Building Authority intends to issue up to $33 million in lease revenue bonds for a city hall and parks, with an estimated $2,303,367 a year in payments. A public hearing is set for Nov. 3.
No recent news stories about Woods Cross. Woods Cross: building authority bonds, tax revenue and water tank has our public-records reporting on the city.