WonderBlock downtown development and parking

A downtown redevelopment project with city-built parking structures, including parking tied to the Second District Court under 2023 agreements. A first amendment to the land transfer and development agreement was approved in October 2024, and a March 2025 update moved court employee parking to the second floor.

Where it stands
Under construction
Type
Development agreement
Location
Near 2525 Grant Avenue, downtown Ogden
Applicant
J. Fisher Company

Every hearing and vote

  1. December 8, 2020 · City Council

    Continental land transfer and development agreement, Wonder Block (Resolution 2020-3)

    Approved · 7-0

    The Redevelopment Agency board adopted Resolution 2020-3 authorizing its executive director to execute a land transfer and development agreement with JF Wonder Block Partners QOZB, LLC for development of property at 2557 Grant Avenue. The results document gives no price or project details.

    • Developer: JF Wonder Block Partners QOZB, LLC
    • Area: Continental Community Reinvestment Area

    Vote: 7-0

  2. April 20, 2021 · City Council

    Wonder Block pre-development agreement (work session)

    Discussed

    In the afternoon joint work session the council received a presentation on a pre-development agreement for the Wonder Block project. The council acting as the Redevelopment Agency took up the agreement for a vote on April 27.

  3. April 27, 2021 · City Council

    Wonder Block predevelopment agreement (RDA Resolution 2021-7)

    Approved · 7-0

    Acting as the Redevelopment Agency, the council adopted Resolution 2021-7 authorizing the executive director to sign a predevelopment services agreement with JF Wonder Block Partners QOZB, LLC.

    Vote: 7-0

  4. June 21, 2022 · City Council

    Budget amendment for WonderBlock pre-development

    Approved · 5-0

    Ordinance 2022-32 amends the budget by $2,500,000 for WonderBlock pre-development costs. At the special Redevelopment Agency meeting, Resolution 2022-5 made the same amendment, 5-0.

    Vote: 5-0

  5. November 15, 2022 · City Council

    WonderBlock sales tax and tax increment pledge agreement

    Approved · 7-0

    Resolution 2022-22 authorized the form of a pledge agreement between the city and the Redevelopment Agency's WonderBlock bonds, set maximum amounts, terms and interest rate, and set a public hearing for Jan. 10, 2023.

    Vote: 7-0

  6. November 15, 2022 · City Council

    RDA bond parameters for WonderBlock (not more than $75 million)

    Approved · 7-0

    Sitting as the Redevelopment Agency, the council adopted Resolution 2022-12 authorizing the issuance and sale of up to $75 million in Sales Tax and Tax Increment Revenue Bonds and an interlocal sales tax pledge agreement, and set a public hearing for Jan. 10, 2023.

    Vote: 7-0

  7. November 15, 2022 · City Council

    Municipal Building Authority bond parameters for parking structures (not more than $85 million)

    Approved · 7-0

    Sitting as the Municipal Building Authority, the council adopted Resolution 2022-2 authorizing up to $85 million in Lease Revenue Bonds, Series 2023, and set a public hearing for Jan. 10, 2023.

    Vote: 7-0

  8. November 15, 2022 · City Council

    Joint work session: WonderBlock, paid parking and project financing

    Discussed

    The council held a fact-finding joint work session with presentations from Ogden Community and Economic Development and financial advisers Lewis Young Robertson & Burningham on the WonderBlock development, a paid parking management system and the financing plan, followed by a public open house.

  9. December 13, 2022 · City Council

    Fact-finding: WonderBlock development and pay parking system

    Discussed

    Community and Economic Development presented the WonderBlock development and a pay parking system, followed by a question and answer period.

  10. December 20, 2022 · City Council work session

    Fact-finding: WonderBlock development and pay parking system

    Discussed

    Ogden Community and Economic Development continued presentations on the WonderBlock development and the pay parking system, with a question and answer period.

  11. January 3, 2023 · City Council

    Work session: Francom Public Safety Building, Union Station and WonderBlock agreements

    Discussed

    The work session covered a capital plan amendment to relocate the Virtra training platform to the Francom Public Safety Building, a budget amendment for that building and Union Station, the amended operating agreement of JF WonderBlock Partners QOZB, LLC, a WonderBlock court parking agreement and a Redevelopment Agency budget amendment for Union Station.

  12. January 10, 2023 · City Council

    WonderBlock sales tax pledge agreement and indenture

    Approved · 4-3

    After a public hearing, Resolution 2023-1 authorized a sales tax agreement and approved a general indenture for Redevelopment Agency Sales Tax and Tax Increment Revenue Bonds for the WonderBlock project.

    Vote: 4-3 (the city results report does not name individual votes)

  13. January 10, 2023 · City Council

    Municipal Building Authority master lease and lease revenue bonds

    Approved · 5-2

    Resolution 2023-3 approved a master lease agreement with the Municipal Building Authority and the sale of not more than $85,000,000 in lease revenue bonds. The Authority separately approved the same by 5-2 (its Resolution 2023-1) for two parking structures.

    Vote: 5-2 (the city results report does not name individual votes)

  14. January 10, 2023 · City Council

    Redevelopment Agency WonderBlock bond parameters

    Approved · 4-3

    Sitting as the Redevelopment Agency, the council adopted Resolution 2023-1 authorizing sales tax and tax increment revenue bonds not to exceed $75,000,000 for the WonderBlock project, after a public hearing.

    Vote: 4-3 (the city results report does not name individual votes)

  15. January 17, 2023 · City Council

    Court parking real estate purchase and access easement

    Approved · 6-1

    Resolution 2023-4 (council) and Resolution 2023-3 (Redevelopment Agency) authorized a real estate purchase contract with the State of Utah, Division of Facilities Construction and Management, for property at approximately 2525 Grant Avenue, with an access easement. The results report does not give the price.

    Vote: 6-1 (the city results report does not name individual votes)

  16. January 17, 2023 · City Council

    Amended WonderBlock operating agreement with JF WonderBlock Partners QOZB, LLC

    Approved · 5-2

    Resolution 2023-4 (Redevelopment Agency) approved the amended and restated operating agreement of JF WonderBlock Partners QOZB, LLC to facilitate development of property at approximately 2557 Grant Avenue.

    Vote: 5-2 (the city results report does not name individual votes)

  17. January 17, 2023 · City Council

    Amended WonderBlock land transfer and development agreement

    Approved · 5-2

    Resolution 2023-5 (Redevelopment Agency) approved an amended and restated land transfer and development agreement with JF WonderBlock Partners QOZB, LLC for property at approximately 2557 Grant Avenue.

    Vote: 5-2 (the city results report does not name individual votes)

  18. February 2, 2023 · City Council

    Joint work session with Ogden School District Board of Education

    Discussed

    The school district presented recent successes and ongoing challenges. The city presented on WonderBlock, a roadmap for developing the Union Station campus, the new Marshall White Recreation Center and homelessness response efforts.

  19. September 10, 2024 · City Council

    WonderBlock land transfer agreement amendment and $4 million bond interest budget amendment

    Discussed

    Community and Economic Development Executive Director Jared Johnson described a first amendment to the Amended and Restated Land Transfer and Development Agreement for WonderBlock, updating phasing and phase names, financial commitments, invoicing and payment procedures, and ownership and representation. Finance Director Justin Sorensen said a separate budget amendment would recognize $4,000,000 in interest income on the $64,220,000 Series 2023 Sales Tax and Tax Increment Revenue Bonds, to fund project development costs, with any excess going to debt service. Both were slated for the October 1 RDA meeting.

  20. March 11, 2025 · City Council

    WonderBlock parking update (work session)

    Discussed

    City Engineer Taylor Nielsen said a 2023 purchase contract lets the Redevelopment Agency acquire seven state-owned parcels used for Second District Court parking in exchange for securing existing parking plus 125 stalls and an option for 100 monthly passes in the WonderBlock east garage. Because placing court employee parking on the first floor is not feasible, the plan moves it to the second floor with visitor parking on several levels. The board approved a first amendment to the land transfer and development agreement in October 2024; staff said the changes are not material, so no council or agency action is needed.