Water meter replacement (Project WU001)

Capital plan project to replace aging water meters and hardware systems. Added to the FY2021-2025 Capital Improvement Plan on Nov. 10, 2020 (Ordinance 2020-52).

Where it stands
Approved
Type
Public project
Location
Citywide

Every hearing and vote

  1. October 13, 2020 · City Council

    Capital plan amendment for water meter replacement (Ordinance 2020-52)

    Approved · 6-0

    By common consent the council set a Nov. 10 public hearing on Ordinance 2020-52, which would add Project WU001 to the FY2021-2025 Capital Improvement Plan for replacing aging water meters and hardware systems.

    Vote: 6-0

  2. November 10, 2020 · City Council

    Capital plan amendment: water meter replacement (Ordinance 2020-52)

    Approved · 6-0

    After a public hearing, the council adopted Ordinance 2020-52 adding Project WU001 to the FY2021-2025 Capital Improvement Plan for replacement of aging water meters and hardware systems.

    Vote: 6-0