Ogden-Hinckley Airport terminal
Capital plan Project AR014 was amended on April 5, 2022 for additional terminal work.
- Where it stands
- Under construction
- Type
- Public project
- Location
- Ogden Hinckley Airport
Every hearing and vote
May 5, 2020 · City Council
Work session: airport master plan and airport terminal roof
Discussed
The work session covered the proposed 2020 Ogden-Hinckley Airport Master Plan, airport terminal roof and infrastructure planning, a fiscal years 2020-2024 Capital Improvement Plan amendment and a budget amendment.
May 12, 2020 · City Council
Ogden-Hinckley Airport Master Plan
No action
Resolution 2020-12, adopting the 2020 Ogden-Hinckley Airport Master Plan, was presented. No action was required; public input was scheduled for May 26, 2020.
May 12, 2020 · City Council
Airport terminal improvements: capital plan and budget amendments
No action · 7-0
The council set May 26 hearings on Ordinance 2020-10, adding Capital Improvement project AR005 for Ogden-Hinckley Airport terminal building improvements, and Ordinance 2020-11, a $320,000 budget amendment for terminal roof improvements and infrastructure upgrades.
May 26, 2020 · City Council
Capital plan amendment: airport terminal building improvements
Approved · 6-0
After a public hearing, the council adopted Ordinance 2020-10, adding Capital Improvement Project AR005 for Ogden-Hinckley Airport terminal building improvements.
May 26, 2020 · City Council
Budget amendment: airport terminal roof and infrastructure, $320,000
Approved · 5-1
The council adopted Ordinance 2020-11, amending the fiscal 2020 budget by $320,000 for airport terminal roof improvements and infrastructure upgrades, on a 5-1 vote. The results report does not name the member who voted no.
May 26, 2020 · City Council
2020 Ogden-Hinckley Airport Master Plan
Approved · 6-0
After receiving public input, the council adopted Resolution 2020-12, the 2020 Ogden-Hinckley Airport Master Plan, on the Planning Commission's report.
April 5, 2022 · City Council
Capital Improvement Plan amendment for Airport terminal project
Approved · 7-0
Ordinance 2022-12 amends Project AR014 for additional work to the terminal at the Ogden Hinckley Airport. The results report gives no dollar figure.