Old airport control tower demolition (Project AR012)

Demolition of the old control tower in the airport terminal building because of structural deficiencies and safety concerns, with a $520,000 budget adjustment. Capital plan and budget ordinances adopted Dec. 15, 2020.

Approved

Type
Public project
Location
Airport terminal building
  1. Dec 15, 2020City Council: Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59)
  2. Dec 1, 2020City Council: Airport control tower demolition: capital plan and budget amendments set for hearing (Ordinan…

In brief

Old airport control tower demolition (Project AR012) appears on 2 recorded agendas, from the City Council meeting of December 1, 2020 to the City Council meeting of December 15, 2020.

On record, it was approved 2 times.

The most recent decision was approved (7-0) at the City Council meeting of December 15, 2020.

Follow the money and project delivery

Old airport control tower demolition (Project AR012)

Approved

  1. Council action

    Approved: Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59) · Agenda and reports Record → · Dec. 15, 2020

  2. Money in the record

    budget: $520,000 — Demolish old airport control tower Record → · Dec. 15, 2020

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. December 15, 2020 · City Council

    Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59)

    Approved · 7-0

    After a public hearing, the council adopted Ordinance 2020-58 adding Project AR012 for demolition of the old control tower in the terminal building, and Ordinance 2020-59 adjusting the FY2021 budget by $520,000 for the demolition because of structural deficiencies and safety concerns.

    Vote: 7-0

  2. December 1, 2020 · City Council

    Airport control tower demolition: capital plan and budget amendments set for hearing (Ordinances 2020-58, 2020-59)

    Approved · 6-0

    By common consent the council set Dec. 15 hearings on adding Project AR012, demolition of the old control tower in the airport terminal building, to the capital plan and on a $520,000 budget increase to demolish it because of structural deficiencies and safety concerns.

    Vote: 6-0