Old airport control tower demolition (Project AR012)

Demolition of the old control tower in the airport terminal building because of structural deficiencies and safety concerns, with a $520,000 budget adjustment. Capital plan and budget ordinances adopted Dec. 15, 2020.

Where it stands
Approved
Type
Public project
Location
Airport terminal building

Every hearing and vote

  1. December 1, 2020 · City Council

    Airport control tower demolition: capital plan and budget amendments set for hearing (Ordinances 2020-58, 2020-59)

    Approved · 6-0

    By common consent the council set Dec. 15 hearings on adding Project AR012, demolition of the old control tower in the airport terminal building, to the capital plan and on a $520,000 budget increase to demolish it because of structural deficiencies and safety concerns.

    Vote: 6-0

  2. December 15, 2020 · City Council

    Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59)

    Approved · 7-0

    After a public hearing, the council adopted Ordinance 2020-58 adding Project AR012 for demolition of the old control tower in the terminal building, and Ordinance 2020-59 adjusting the FY2021 budget by $520,000 for the demolition because of structural deficiencies and safety concerns.

    Vote: 7-0