Old airport control tower demolition (Project AR012)
Demolition of the old control tower in the airport terminal building because of structural deficiencies and safety concerns, with a $520,000 budget adjustment. Capital plan and budget ordinances adopted Dec. 15, 2020.
Approved
- Type
- Public project
- Location
- Airport terminal building
- City Council: Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59)
- City Council: Airport control tower demolition: capital plan and budget amendments set for hearing (Ordinan…
In brief
Old airport control tower demolition (Project AR012) appears on 2 recorded agendas, from the City Council meeting of December 1, 2020 to the City Council meeting of December 15, 2020.
On record, it was approved 2 times.
The most recent decision was approved (7-0) at the City Council meeting of December 15, 2020.
Follow the money and project delivery
Old airport control tower demolition (Project AR012)
- Council action
Approved: Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59) · Agenda and reports Record → · Dec. 15, 2020
- Money in the record
budget: $520,000 — Demolish old airport control tower Record → · Dec. 15, 2020
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
December 15, 2020 · City Council
Airport control tower demolition: capital plan and budget (Ordinances 2020-58, 2020-59)
Approved · 7-0
After a public hearing, the council adopted Ordinance 2020-58 adding Project AR012 for demolition of the old control tower in the terminal building, and Ordinance 2020-59 adjusting the FY2021 budget by $520,000 for the demolition because of structural deficiencies and safety concerns.
December 1, 2020 · City Council
Airport control tower demolition: capital plan and budget amendments set for hearing (Ordinances 2020-58, 2020-59)
Approved · 6-0
By common consent the council set Dec. 15 hearings on adding Project AR012, demolition of the old control tower in the airport terminal building, to the capital plan and on a $520,000 budget increase to demolish it because of structural deficiencies and safety concerns.