Wednesday, October 14, 2026TheUtah Ledger
American Fork

Contracts and spending

Who American Fork pays, for what, and how the vendor was chosen: every contract, bid award, change order, purchase, grant and land deal that came before the City Council, from the meeting minutes and packets, plus what the city paid its biggest vendors from the state transparency site.

Approved in meetings we cover
$4542.8 million
Line items
761
Vendors
206

Every approval, newest first

DateWho and whatAmount
Tue, Mar 19Utah Division of Water Resources: Pressurized irrigation metering (received prior year)
FY2025 water, pressurized irrigation, sewer, storm drain and sanitation funds · Discussed
$6.60 million
Tue, Mar 21Utah Division of Water Resources: Pressurized irrigation grant (PI metering)
FY2024 water, sewer and storm drain funds · Discussed
$6.60 million