Thursday, October 15, 2026The Utah Ledger

Everything Utah, every day.

Sandy · City Council work session

Sandy council holds public meeting on arguments for $21 million Fire Station 31 bond; voters decide Nov. 21

November 7, 2023, 5:15 p.m. · Council Chambers, Sandy City Hall, 10000 Centennial Parkway, and Zoom

The Sandy City Council held a public meeting on arguments for and against up to $21,000,000 in general obligation bonds for a new Fire Station 31. No argument against was submitted, and voters decide Nov. 21, 2023. Three speakers supported the bond. The only votes were the consent calendar and adjournment.

From the approved minutes. Updated October 14, 2026.

Decisions at a glance

Agenda, item by item

  1. Item 2 · Presentation

    Special recognition: Girl Scout Troop 294 Bronze Award

    Discussed

    Two scouts were recognized for building bird houses and installing them at Sego Lily Gardens. Each Troop 294 girl received a U.S. flag and a Sandy City pin, and the mayor presented certificates.

  2. Item 3-5 · Other

    Consent: Oct. 10 and Oct. 24 draft minutes

    Approved

    Approved by unanimous voice vote.

    Moved by Council Member Zach Robinson, seconded by Council Member Marci Houseman

  3. Item 6 · Public safety

    Public meeting on arguments for and against up to $21,000,000 in general obligation bonds for Fire Station 31

    Discussed

    Administrative Services Director Brian Kelley reviewed the election timeline; voter information pamphlets were mailed to households with registered voters. No argument against the bond was submitted and the argument in favor was read. Voters decide Nov. 21, 2023, and the bonds would pay to build and equip the new station. Cathy Spuck supported the bond, citing leaks, foundation cracks and limited office space at the current station. Steve Van Maren supported it and asked whether costs were final and whether the location had changed. Sue Zabel supported it and asked about the timeline and whether property taxes from new development would help fund it. No action was taken.

    • Bond$21.0 million General obligation bonds, up to $21,000,000, to build and equip Fire Station 31 (voters decide Nov. 21, 2023). Paid from Property tax, if approved by voters

    Follow Fire Station 31 rebuild and general obligation bond in the development tracker →

What residents said

Fire Station 31 bondSewer fees

Steve Van Maren also opposed South Valley Sewer District fee increases and said residents should know the revenue bond terms.