Holladay council adopts Spring Lane Park design plan 6-0; FEMA grant of $1.7 million received for City Hall seismic work

August 20, 2026, 6:00 p.m. · Temporary City Council Chambers, 3330 South 1300 East, Millcreek

On Aug. 20 the council voted 6-0 to adopt the Spring Lane Park design plan. Staff reported that the FEMA grant for the City Hall seismic project, a total of $1.7 million with a federal share of $1.275 million, was received and signed that day. A work meeting heard that City Hall completion remains on track for mid-September 2027.

From the approved minutes. Updated October 14, 2026.

Decisions at a glance

Agenda, item by item

  1. Item V · Parks

    Resolution 2026-26: Spring Lane Park design plan

    Approved · 6-0 · Spring Lane Elementary site

    Final version of the plan reviewed at the previous meeting. No dollar amounts or address were given.

    Moved by Council Member Natalie Bradley, seconded by Council Member Drew Quinn. Vote: 6-0

    Follow Spring Lane Elementary reuse and City Hall seismic retrofit in the development tracker →

  2. Item VI · Budget

    City manager report: FEMA grant and Creative Aging application

    Discussed

    The FEMA agreement was signed that day, obligating a grant of $1.7 million (federal portion $1.275 million; a local match is required) for construction. Staff are preparing a Creative Aging application of up to $3,000 with no match.

    • Grant$1.70 million to FEMA City Hall seismic retrofit grant; federal portion $1,275,000, local match required. Paid from Federal
    • Grant$3,000 Creative Aging grant application, up to

    Follow Spring Lane Elementary reuse and City Hall seismic retrofit in the development tracker →

  3. Item VIII.a · Roads and utilities

    Work meeting: City Hall construction update

    Discussed

    Interior demolition should wrap up the following week; electrical and plumbing demolition is complete. Seismic work may be delayed to meet grant requirements and completion remains on track for mid-September 2027. A request for proposals is being pursued for phase III auditorium work.

    Follow Spring Lane Elementary reuse and City Hall seismic retrofit in the development tracker →