Logan council budget workshop covers $29.97 million bioreactor, electric transformers, police and public works budgets
May 27, 2025
At a second budget workshop with no votes, staff presented Light & Power, Police, Environmental and Public Works budgets, including a $29,968,000 fourth bioreactor expansion with a funding gap of about $2.5 million and a $4 million reserve transfer for substation transformers. Members discussed adding a communications position.
From the approved minutes. Updated October 14, 2026.
Decisions at a glance
| Item | Result |
|---|---|
| Light & Power budget | Discussed |
| Police and dispatch budget | Discussed |
| Environmental budgets: solid waste, wastewater, bioreactor | Discussed |
| Public Works budget | Discussed |
| General questions and budget timeline | Discussed |
Agenda, item by item
Item 2 · Budget
Light & Power budget
Discussed
Director Mark Montgomery presented a 2026 budget of $48,270,319 (total expense $52,270,319), a $4,000,000 reserve transfer for Substation 1 transformers, $31,595,000 for UAMPS power purchases and $2,000,000 for natural gas fuel. Only two of five transformers are needed now and none have been ordered pending budget approval. Council Member López asked about tariffs; Montgomery said most are U.S.-made but some components come from limited global sources.
- Budget$48.3 million
- Budget$4.00 million
- Purchase$31.6 million to UAMPS
- Budget$2.00 million
Item 3 · Budget
Police and dispatch budget
Discussed
Chief Jeff Simmons reported 120 staff including 63 sworn officers and 21 dispatchers, a police budget of $10,581,231 and a dispatch budget of $2,675,727. Additional funding includes $149,949 in alcohol enforcement funds and a $45,000 JAG task force grant. There were 2,341 reported offenses in 2024. Simmons named competitive pay, growth and event security as concerns; López asked for per-capita charts.
- Budget$10.6 million
- Budget$2.68 million
Item 4 · Budget
Environmental budgets: solid waste, wastewater, bioreactor
Discussed
Director Tyler Richards proposed solid waste revenue and expense of $18,347,897, a $3,825,000 construction and demolition transfer station and a green waste pad backed by a $4,000,000 EPA grant and $4,000,000 city match. The biosolids expansion drew bids of $6,456,576 to $6,978,000, with a $5,000,000 federal grant. Bioreactor 4 would raise plant capacity from 18 to 24 million gallons a day at $29,968,000 ($19,835,000 base plus $10,133,000 alternate); listed sources total $27,477,615, about $2.49 million short, and the minutes do not explain the gap. Richards said the state would lend, not grant, funds, which would require bonding, and that the landfill has about 2.5 years of life left.
- Budget$30.0 million
- Budget$6.98 million
- Grant$4.00 million to U.S. EPA
- Budget$3.83 million
Item 5 · Budget
Public Works budget
Discussed
Director Paul Lindhardt and manager Sam Odd said fiscal 2025 delivered about $30 million in capital projects. Fiscal 2026 plans include the 1000 North and 600 West intersection (summer 2026, with $3,200,000 from the Cache Council of Governments, pending approval), Canyon Road, $200,000 for sidewalks, 100 East waterline work and 400 North sewer work. A water rate proposal would reach the council in three to four months, and a Canyon Road neighborhood committee was expected by the end of June.
- Grant$3.20 million to Cache Council of Governments
- Budget$200,000
Item 6 · Budget
General questions and budget timeline
Discussed
Anderson said electric and water rates will return after the budget, with staged electric increases and tiered water pricing under a state directive. The budget hearing is June 17 and the truth-in-taxation hearing August 7 at 6 p.m. Chair Simmonds proposed an intern or part-time public relations role; Anderson cautioned against a council-funded position reporting to the mayor and said a hire would displace a firefighter or officer hire. Council Members Mark Anderson and Amy Anderson and López supported better communication; Johnson was not opposed but noted the difficulty of two-way dialogue.
What residents said
Wastewater plant fundingUtility ratesCity communications