Tabiona water project

Tabiona's water line project, designed by Sunrise Engineering and built by Johansson Construction, will bore under tribal parcels so it can proceed before the remaining easements are final. The council approved a change order of about $411,000 in August 2026; leftover funds would replace older fire hydrants.

Under construction

Type
Public project
Applicant
Town of Tabiona

In brief

Tabiona water project appears on one recorded agenda: the City Council meeting of August 11, 2026.

On record, it was approved once.

The most recent decision was approved (4-0) at the City Council meeting of August 11, 2026.

Follow the money and project delivery

Tabiona water project

Under construction

  1. Council action

    Approved: Water project change order for boring under tribal parcels · Approved minutes Record → · Aug. 11, 2026

  2. Money in the record

    change-order: $411,000 — Boring through tribal parcels for the water project Record → · Aug. 11, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. August 11, 2026 · City Council

    Water project change order for boring under tribal parcels

    Approved · 4-0

    Jeff McCarty of Sunrise Engineering presented a revised plan: Johansson Construction is willing to bore through the tribal parcels, allowing the town to finish the project without completing the remaining easements. The proposed change order is about $411,000. The council approved it and authorized Johansson to proceed. Any project funds left over would buy new fire hydrants to replace older ones.

    • Engineer: Sunrise Engineering
    • Remaining funds: new fire hydrants

    Moved by Council Member Jones, seconded by Council Member Jacob Hughes. Vote: All in favor