New waterline project
A new waterline funded in part by a 60% loan will be bid after documents are final; the town's 188 customers face an $11 to $15 monthly bill increase.
Proposed
- Type
- Public project
- Applicant
- Town of Sigurd
- Location
- West of the fence near the old railroad property
In brief
New waterline project appears on one recorded agenda: the City Council meeting of September 16, 2026.
Follow the money and project delivery
New waterline project
- Council action
No approval or denial linked in the records collected.
- Money in the record
other: $26,000 — Water loan update reviewed Record → · Sept. 16, 2026
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
September 16, 2026 · City Council
Water loan and waterline project
Discussed
Engineers from Jones & DeMille reviewed a $26,000 update to the 60% water loan and an $11 to $15 water bill increase for 188 customers. The new waterline alignment moves west of the fence near the old railroad property, crews must keep 3 feet from a gas line crossing, and temporary service lines will be used during construction. Bidding is expected to take three weeks once documents are final.