Murray's audited reports list property tax rebates to three Fireclay developers. For one, Streit Avida, the fiscal 2025 table shows payments $279,261 above its listed maximum, and its prior-years figure doesn't match the year before. The records reviewed don't explain the differences.
Continuing story: Auditing Murray
Murray's Redevelopment Agency rebates property tax increment to developers in its Fireclay area under agreements that began in 2007. The agency says the recipient pays its tax bill, and once the provisions of the agreement are verified as met, the agreed amount is rebated. [1]
The fiscal 2025 audited report lists $750,606 in rebates that year: $376,534 to Streit Avida, LLC, $119,020 to Parley's Partners, LLC and $255,052 to Hamlet Development. All three agreements expire in 2033. [1]
The city's budget shows $750,606 in Fireclay private reimbursements in fiscal 2025, an estimated $775,000 in fiscal 2026 and $850,000 budgeted for fiscal 2027. It says these expenditures are based on a percentage of increment revenue. [3]
The Streit Avida figures
The fiscal 2025 table lists $376,534 in rebates to Streit Avida that year and $2,941,844 in prior years. Those add up to $3,318,378. The same row lists a total maximum abatement of $3,039,117, which is $279,261 less. [1]
The fiscal 2024 table lists Streit Avida with $385,707 that year and $1,508,312 in prior years, $1,894,019 in all, and a maximum of $4,772,752. The fiscal 2025 prior-years figure of $2,941,844 is $1,047,825 more than that total. [2][1]
For Parley's Partners and Hamlet Development, the 2024 current-year and prior-year figures add up exactly to the prior-years figures in the 2025 table: $864,119 and $1,879,872. Parley's Partners' listed maximum fell from $2,498,588 to $1,873,941. [2][1]
A recipient leaves the table
The 2024 table also lists Murray TOD Owner, LLC, with no rebate that year, $451,028 in prior years and a maximum of $451,028. It does not appear in the 2025 table. [2][1]
The totals change as well. The 2024 table's current and prior-year rebates add up to $5,089,038, while the 2025 table's prior-years total is $5,685,835, or $596,797 more. The total of the listed maximums fell from $11,051,230 to $8,241,920. [2][1]
The reports reviewed do not explain the changes.
The wider redevelopment picture
The same note reports $3,084,108 in tax increment collected across project areas in fiscal 2025 and $1,388,382 in tax increment distributions. The Fireclay table covers a subset of that activity. [1]
It says the agency entered into an agreement on July 30, 2021, with Jesse Knight Legacy Center, LLC for up to $2,500,000 for a professional office and entrepreneurial center in the Ore Sampling Mill area. As of June 30, 2025, it says, no reimbursement was due because the project had not been completed. [1]
This story compares figures in published tables. The differences are not an established overpayment, a breached cap or missing money. An amendment, a change in how recipients are grouped, a reporting change or a table error could account for them; the records reviewed do not say which.
Sources
- Murray City · FY2025 annual comprehensive financial report, Note 15 redevelopment agency and tax abatements
- Murray City · FY2024 annual comprehensive financial report, Note 15 redevelopment agency and tax abatements
- Murray City · FY2027 final budget, RDA Fireclay area
Reporting by The Utah Ledger from the public records above. AI-assisted, checked against those records.